Who Pays for a Dormant Grid Slot? A Policy & Regulation Deep Read of the Senate Permitting Bill | MyTechDailyNews

By Ruby Cook · MyTechDailyNews Policy & Regulation desk · Tech Daily · hello@techdaily.com

Faster approvals don't clean up a grid queue if the approvals stay free. Unless queue positions and transmission corridor rights carry deposits, deadlines and expiry dates, the Senate permitting bill risks minting the cheapest option market in energy history. The proof already exists: since 2023, PJM has cut its interconnection backlog from above 140 GW to roughly 46 GW by raising the cost of holding a slot.

What happened — and why the coalition looks so strange

The bill is the Bipartisan American Affordability and Jobs Act, a 417-page Senate draft released in late September, according to JD Supra. Congress was still debating it on Thursday, November 12, with a floor vote expected within days — we walked the floor arithmetic in our earlier read on the seventy-three votes behind BAAJA. The scope runs wide: a federal buildout of long-distance transmission, a reworked National Environmental Policy Act, less state authority under the Clean Water Act, more state authority under the Endangered Species Act, per the Bipartisan Policy Center explainer.

The coalition is a curiosity. Evergreen Action — a climate group built by alumni of Jay Inslee's 2020 campaign — is all in. The Wilderness Society and Earthjustice say no. Sierra Club wants it rewritten, Al Gore is a no, and the AFL-CIO, the International Brotherhood of Electrical Workers and the National Urban League are yes votes. What nearly every position paper skips is the dull question underneath: what happens when a holder takes the approval and declines to build?

Why does a free grid slot behave like an option?

Vocabulary first, since this is jargon country. An interconnection queue is the waiting list to plug a power project into the grid. Filing has historically been cheap, so developers filed early and often — frequently the same project in several places at once, to keep choices open, as the Institute for American Manufacturing's queue primer explains. Under the old serial study rules, one speculative withdrawal forced every project behind it through a restudy, waits stretched, and defensive multi-filing started to look rational even to serious developers.

The old design's bill was steep. Before 2023, PJM's serial process stacked a backlog above 140 GW, with some resources waiting more than five years, per Introl's analysis. A new generator in PJM needs about eight years to reach operation while the capacity auction pricing its revenue looks ahead only two to three years. In plain terms, a queue position worked like a financial option: a right without an obligation, at a premium near zero. Nobody walks away from that trade.

The 2023 cleanup worked because holding a slot got expensive. FERC's Order No. 2023 brought higher withdrawal penalties and milestone-based study requirements, and it now requires a commercial readiness deposit at the start of each cluster study, on top of initial study deposits that run between 55,000 and 250,000 dollars, per FERC's own explainer and a Hunton Andrews Kurth summary. Many RTOs and ISOs raised deposits alongside, as a Sina Finance review of queue distortion recounts. One sign the fees actually bite: law firms now advise developers on financing those deposits, which lenders only do for costs that matter, per a Foley & Lardner note on deposit financing.

The demand-side read agrees. Lawrence Berkeley National Laboratory's 2025 queue report describes an American queue heavy with speculative, eventually infeasible projects, where developers hold overlapping applications for one project and drop hundreds of megawatts of phantom capacity in a single stroke once a site is chosen. The lab's latest data put the national scale at roughly 8,200 active projects — about 1,312 GW of generation plus some 749 GW of storage as of the end of 2025 — with roughly 750 GW withdrawn during 2025 alone, per LBNL's Queued Up data page. That withdrawn pile is what pricing flushed out. It's also why "data centers are more than 90 percent of new power requests" deserves a squint: those figures come from queue filings, and a queue counts applications, most of which die without ever drawing a watt.

What does the bill speed up, and what does it leave free?

The draft's accelerators are real. Any party holding grid data needed for an interconnection, facilities, feasibility, or affected-system study must produce it within 15 days, per JD Supra's bill analysis; the 150-day review clock matches the House-passed SPEED Act; and the Department of Energy would study transmission congestion every three years, per the Bipartisan Policy Center explainer. All worth supporting — my beef is the unpriced remainder. Every week shaved off a study cycle makes a dormant position cheaper to carry, and nothing in the public summaries gives an approval an expiry date tied to construction.

The demand side shows what free options attract. ERCOT is carrying more than 474 GW of interconnection requests, about nine in ten tied to data centers, spread across more than 1,800 projects — a stack more than five times the historical peak load, per a briefing on the Texas standoff published on Eastmoney's Fortune channel. Texas paused new data center interconnection approvals by executive order in August 2026 and froze related environmental permits on September 21; exit polling on November 3 found 75 percent of surveyed voters against new data centers in their own communities. Compute gear lands on quarterly cycles while grid increments arrive on decade scales, a timing gap NetEase's analysis of AI infrastructure timing describes. Filing everywhere is the hedge against that gap — and 474 GW is what the hedge looks like in aggregate.

Who pays for idle capacity is no longer hypothetical. Virginia legislature researchers put the potential household tab at an extra 14 to 37 dollars a month in generation and transmission costs by 2040, in real terms, absent rate restructuring, per the Introl analysis. Virginia regulators cut Dominion's requested increases for 2026 and 2027, 822 million and 345 million dollars, down to approved amounts of 565.7 million and 209.9 million dollars. PJM's new minimums, effective January 1, 2027, require documented commitments covering at least 85 percent of contract demand at the transmission and distribution level and 60 percent at the generation level. Voters punish cost shifting and regulators are moving to commitment-based rules; a bill that accelerates approvals while letting granted rights idle for free is swimming against its own politics.

What would a priced queue actually look like?

The parts already exist on both sides of the Atlantic. France's reform runs on a milestone logic — clear documented steps at specified dates or surrender the queue position — and it deliberately stops short of demanding all permits and full financing upfront; the backdrop is 33 GW of industrial capacity stuck behind outdated rules, per Journal du Progressiste. Stateside, ERCOT's zero-batch track makes developers prove project maturity before entering a regional transmission study, SPP runs its HILLGA framework for large loads, PJM operates a dedicated large-load procedure, and NRG Energy has proposed competitive open-recruitment windows with time-limited bidding charging large users for the grid upgrades they trigger, per Sina's coverage of the commitment-first shift. The same design questions travel globally too — we stress-tested them in our case review of what grid-queue reforms teach COP31's 35x35 pledge.

Commitment mechanisms, side by side

FrameworkMechanismWhat it pricesStatus
PJM post-2023 reformsHigher withdrawal penalties, milestone-based cluster studiesThe wait itselfBacklog above 140 GW cut to roughly 46 GW
FERC Order No. 202355,000–250,000 dollar initial study deposits; readiness deposit at each cluster studyFiling and staying in lineIn effect for new requests
France milestone systemDocumented milestones or surrender the slot; no full financing demanded upfrontDormancyYoung; 33 GW backlog prompted the reform
ERCOT zero-batch trackMaturity proof before a regional transmission studyEntryOperating in Texas
SPP HILLGA / PJM large-load procedureCommitment screens for large loadsDemand claimsOperating
The Senate draft15-day data clause, 150-day clock, triennial congestion studyNothing yet — no expiry, deposit or reallocationAwaiting floor vote

Against that backdrop, three clauses would fit the bill's existing architecture, no new theory required. A withdrawal deadline keyed to study milestones, so an inactive application exits before it forces another restudy cycle. A staged deposit — modest at filing, stepped up at each milestone, refunded or credited against interconnection costs on completion — which puts a carrying cost on the option without prohibiting it. And automatic reallocation for corridor approvals, so a transmission right that misses construction milestones returns to the planning pool instead of aging in a drawer. Corridor language deserves equal billing with queue language: the federal buildout this bill envisions will mint precisely these long-lived approvals.

Even the bill's champions concede the implementation layer decides outcomes. On the Shift Key podcast, hosted by Heatmap News founding editor Robinson Meyer, Evergreen Action executive director Lena Moffitt and vice president of policy Pete Wyckoff argued that major changes at the Federal Energy Regulatory Commission remain necessary even if the legislation clears. Moffitt's pre-vote statement held that no better deal is around the corner and the country has to start building clean energy at scale. A coalition endorsing speed while admitting regulators must finish the job should have no trouble accepting dormancy clauses — those clauses are the finishing work.

Who wins and who loses? The objection that deserves an answer

The strongest counterargument concerns who survives a priced queue. Deposits and maturity screens filter by balance sheet: a hyperscaler or a utility affiliate can post staged deposits across many sites without noticing, a small storage developer cannot, and that developer may genuinely need the queue data, the study results and the preliminary engineering to raise the financing that would make it mature. Compel commitment before the information that produces commitment exists, and the queue cleans up by washing out small players. A second objection, drawn from the Data Center Coalition's filings, holds that delays stem mainly from undersized transmission planning and missing long-range planning, so penalties treat a symptom. A third is plain: France's milestone system and ERCOT's zero-batch track are young, and the evidence base is thin.

Each objection has weight, and each meets an answer in data that already exist. PJM's queue shed its duplicates after 2023 while the reformed process kept clearing projects, which suggests penalties remove filings that were never going to be financed anyway. A refundable, milestone-staged deposit sized to project capacity keeps the multi-site strategy legal while giving it a carrying cost a small shop can budget for. On planning, the bill's triennial congestion study widens the lens, and wider planning reduces the incentive to file defensively everywhere; fewer defensive filings in turn make stricter queue discipline cheaper to bear. On evidence, I concede the point and convert it into a test: if completed capacity in jurisdictions running commitment-first rules falls over the next two years relative to jurisdictions without them, the case for dormancy penalties collapses and this argument is wrong. If withdrawals keep shedding duplicate megawatts while completions hold, the case stands.

What should compliance and policy teams do now?

  • Developers holding multi-site positions: audit every queue slot against its next milestone date and model a staged-deposit carrying cost before the vote lands — under zero-batch-style screens, documented site control and financing readiness are the entry ticket.
  • Legal and compliance staff: track FERC dockets and state commissions for lapse or dormancy clauses on corridor and capacity rights, and re-run demand forecasts against PJM's 85/60 percent documented-commitment minimums that take effect January 1, 2027.
  • Analysts and investors: treat queue filings as applications, not demand — discount "90 percent of new requests" claims and read the Virginia pattern (822 million and 345 million dollars requested, 565.7 million and 209.9 million approved) as regulators repricing speculative demand.
  • Everyone waiting on the bill: don't. FERC Order 2023's deposit mechanics already apply to new requests, so priced-queue economics are live today.

Dates to watch

The calendar is concrete: the Senate vote following the November 12 debate; ERCOT's queue review report due December 10, 2026; the Texas legislative session running January 12 through May 31, 2027, where the pauses could harden into law. PJM's reformed queue is supposed to finish processing by the end of 2026, so its withdrawal and completion statistics will be the first clean test of whether discipline kills real projects. Dustin Meyer, who has testified before the U.S. Senate on the need for reform, put the consensus plainly on LinkedIn: "We work a lot of wonky/technical issues, but permitting reform isn't one of them." The dispute is over the fix — and the fix has to cover the back of the process as well as the front.

So here's the question I'll be watching for the next two years: once holding an approval costs rent, how much of those 474 GW of Texas requests turns into steel and wire, and how much turns into cancelled filings? Check the withdrawal statistics before you believe any press release — including PJM's.

FAQ

Why did PJM's queue shrink so fast?

Because holding a slot stopped being free. FERC's 2023 reforms added withdrawal penalties, milestone-based studies and readiness deposits — including initial study deposits of 55,000 to 250,000 dollars — and PJM's backlog fell from above 140 GW to roughly 46 GW as speculative and duplicate filings exited.

Does pricing queue slots shut out small developers?

It can, if deposits are large and non-refundable. A refundable, milestone-staged deposit sized to project capacity keeps a legitimate multi-site strategy legal while adding a carrying cost a small shop can budget for.

What's the difference between a queue position and a corridor approval?

A queue position is a generator's place in line to connect to the grid; a corridor approval is a right to build transmission across a route. Both can sit idle for years, which is why both need deadlines and reallocation rules.

Where can I check queue numbers myself?

Lawrence Berkeley National Laboratory's Queued Up series — roughly 8,200 active projects, 1,312 GW of generation plus some 749 GW of storage at the end of 2025 — plus the PJM and ERCOT queue pages. Read them as applications filed, not megawatts that will run.

References

  • BAAJA Blast: What the Senate Permitting Bill Means for Transmission Developers (JD Supra)
  • Senate Unveils Bipartisan Permitting Overhaul (JD Supra)
  • Explaining the Senate Permitting Bill, the Bipartisan American Affordability and Jobs Act (Bipartisan Policy Center)
  • Explainer on the Interconnection Final Rule (FERC)
  • FERC's Order No. 2023 Aims at Improving and Expediting the Generator Interconnection Process (Hunton Andrews Kurth)
  • Interconnection Deposit Financing: A Novel Approach (Foley & Lardner via JD Supra)
  • Queued Up: Characteristics of Power Plants Seeking Grid Interconnection (Lawrence Berkeley National Laboratory)
  • The Interconnection Queue (Institute for American Manufacturing)
  • PJM Grid Crisis and Data Center Capacity Shortfall Analysis (Introl)
  • In France 33 GW of Industrial Capacity Stuck by Outdated Rules (Journal du Progressiste)
  • Speculative Queue Filings Distort Perceptions of Grid Demand (Sina Finance)
  • Texas 2026: Interconnection and Permitting Pauses Ahead of the Legislative Session (Eastmoney Fortune)
  • Permitting Reform and AI Infrastructure Timing (NetEase)
  • Duplicate AI Filings Push Grid Planning Toward Commitment First (Sina News)
  • Dustin Meyer on Permitting Reform (LinkedIn)

Questions or tips on grid queue policy? Write to Ruby Cook at hello@techdaily.com — MyTechDailyNews, a Tech Daily publication.

Related reading

  • Permitting Bill Compared: Approval Miles vs. Delivered Megawatt-Hours | MyTechDailyNews Policy and Regulation
  • Can an AI Data Centre Really Bend Its Load? A Proof Checklist for Power Pacts | MyTechDailyNews Policy and Regulation
Brand logo

Tech Daily

Your Daily Source for Consumer Tech, Policy & Communications

HardwarePolicy & RegulationSoftwareCommunicationsConsumer ElectronicsGeneralAPAC EdmGrowthAbout Us

© 2026 Tech Daily.

Cookie Notice

We use cookies to improve your experience and analyze website traffic. Read our Privacy Policy to learn more.