In Antalya the COP31 presidency put a single figure on the screen — electricity at 35% of final energy use by 2035 — and the applause was for a number nobody in the room has agreed how to check. The short answer: the pledge counts a share, not a connection rate, and two live reforms in Britain and the United States already publish the indicators that would close the gap.
Both cases are useful for an unglamorous reason. Britain was forced to rank a queue it could no longer defend; the United States was forced to count withdrawals after a decade of speculative filings. Neither reform was written for a climate target, which is precisely why the mechanics travel.
Turkey's presidency wants electricity at 35% of the world's final energy use by 2035, and the accompanying text says nothing about how anyone would verify that the capacity behind the number actually connects. The pledge is a percentage, and percentages move without a single new line being energized.
Reporting from the opening session put electricity at 21% of end-use energy and cited a Rhodium Group projection of 28% by 2035. The World Benchmarking Alliance describes the proposal as a climb from roughly 23% of final energy consumption, and an independent COP31 analysis uses the same 23% starting point. Two percentage points looks like bookkeeping until you notice what it decides: who gets to claim success.
The boundary is the reason. End-use energy and final energy consumption cut the system in different places, and efficiency gains, fuel switching and international bunkers land on different sides of the line. Shift the convention and a government can report 35% built on a redefinition plus a decade of efficiency improvement while connecting almost nothing.
Even with the boundary fixed, the climb is steep. Rhodium's central path reaches 28%, so seven points have to be closed in ten years — requiring slow growth in final demand, fast scaling of clean generation, and networks that connect new supply and new load at a pace most systems have rarely managed. The first two show up in energy statistics; the third shows up in no headline indicator at all. And a share can also rise with no wire: trim final demand, hold electricity use steady, and the percentage climbs while the grid does nothing new.
Britain's answer was to stop treating the queue as a line and start treating it as a filter. First-come-first-served gave way to two tests — readiness and strategic alignment — with the criteria published so developers could argue with the scoring instead of with each other.
Ofgem issued its final decision on the connections reform package, TMO4+, on 15 April 2025, opening a 56-day licence standstill that ran to 10 June 2025 (Simmons & Simmons). Before the reform, NESO's connections publications described a GB transmission queue above 700 GW (NESO). Gate 2 then did the sorting: about 217 GW of Gate 2-ready capacity was not prioritised because it failed the strategic-alignment test, and the resulting pipeline landed at roughly 100 GW (Walker Morris).
Read that as a rate rather than a trophy. The purpose was never to shrink a queue; it was to generate an annual answer to "how many projects cleared the gate, and which ones were told to wait?" Ofgem has since consulted on a returnable commitment fee for large data-centre connection requests, aimed at deterring non-viable applicants (Ofgem consultation, July 2026).
The lesson for a COP annex is unglamorous: a regulator-approved methodology, published criteria and a scheduled re-ranking produce a comparable series. Britain's own electrification scorecard shows how far rules can run ahead of delivery, splitting 82% for enabling conditions against 38% for deployment.
The American reform attacked the study process itself, and the more useful legacy for COP31 is what became countable. FERC Order 2023 moved regional grids to cluster studies, tightened readiness requirements including a 90% site-control threshold, imposed withdrawal penalties and spread network-upgrade costs across clusters; the D.C. Circuit later upheld the package (RTO Insider).
Berkeley Lab's Queued Up series then produced the kind of figures a share target cannot: at the end of 2025, about 8,200 projects were seeking transmission interconnection, representing 1,312 GW of generation and roughly 749 GW of storage — just over 2,000 GW in total (Queued Up: 2026 Edition). The queue did not grow that year. Withdrawals of about 750 GW outran roughly 600 GW of new requests, and active volume fell around 10%.
Attrition is the variable worth staring at. The prior edition found 61% of active capacity — some 1,400 GW — carrying a proposed online date before 2028, while only 18%, about 408 GW, held a draft or executed interconnection agreement (Queued Up: 2025 Edition). Wait times have lengthened in parallel: the typical stretch from connection request to commercial operation rose from under two years for projects built in 2000-2007 to a median of five years for projects built in 2023 (Queued Up: 2024 Edition).
Look further back and the funnel narrows hard. Among requests filed between 2000 and 2018, just 19% of projects and 14% of capacity reached commercial operation by the end of 2023 (Berkeley Lab). Not one of these numbers needed a new statistical agency — they came from disclosures operators already file, cleaned and published on an annual cycle.
They prove the yardstick is a design choice rather than a data impossibility, and they disagree about which end of the process to measure — which is why a pledge should borrow both.
| Dimension | Britain (TMO4+ / Gate 2) | United States (Order 2023 + Queued Up) | What a 35x35 annex should borrow |
|---|---|---|---|
| What the reform changed | Readiness and strategic-alignment tests replace queue order | Cluster studies, 90% site control, withdrawal penalties, shared upgrade costs | Rules that create comparable outcomes, not just faster processing |
| What gets published | Regulator-approved criteria and methodology, plus a re-ranked pipeline | Annual project counts, megawatts, withdrawal volumes, share holding an agreement | A fixed annual series with stable definitions |
| Visible result | Queue above 700 GW before reform; roughly 100 GW prioritised after Gate 2 | About 2,061 GW active at end-2025; roughly 750 GW withdrawn that year | Stock and flow reported together |
| Transferable lesson | Admission rate per cycle | Survival rate and cost allocation | Queue length, withdrawal rate, agreement share, upgrade-cost split |
The last row is the one to carry into a negotiating room. Britain measures who gets in; the United States measures who survives. A pledge about capacity that actually runs needs both numbers for the same year.
The global total everyone quotes is a practitioner estimate, not a census — which is exactly the problem. Writing on LinkedIn, Alicia Argüello put more than 2,500 GW of renewable generation, storage and large-load projects waiting for connection worldwide (Alicia Argüello). Treat it as an order of magnitude; even at that strength it locates the bottleneck.
The IEA's Electricity 2026 assessment reports grid connection queues at record levels worldwide and calls for annual grid investment to rise sharply through 2030 to keep pace with demand (IEA). Neither that report nor the 2,500 GW figure gives a market-by-market withdrawal rate or a cost-allocation rule, and those are the variables where projects actually die.
Two structural gaps sit underneath. A diagnosis of China's distribution-grid reforms found that available capacity is now disclosed, but the mechanisms separating speculative queue positions from viable projects, the triggers that release held capacity and the principles for sharing upgrade costs still rest on administrative coordination rather than published rules (sdg-china.net) — the same pattern in a different power system. For Africa, the argument is framed around connections, cooking and who pays, with grid finance treated as the binding constraint ahead of the share itself (ESI Africa; ecoltdgroup).
Where the network was never built to reach a region, the queue is less a list of stalled projects than a list of projects nobody proposed. No indicator fixes that. A cost-allocation rule at least makes the bill visible.
The strongest objection is political, not technical: 35x35 is an instrument for moving finance, and a queue baseline over-specifies it. The Green Grids Initiative welcomed the target on roughly those grounds, crediting it with placing grids at the centre of the electrification agenda (Green Grids Initiative).
A sharper version comes from the countries the pledge is meant to help. Any indicator attached to a voluntary target can later be used as a test. The second global stocktake opens at this conference and is scheduled to conclude at COP33 in 2028, with technical work starting in mid-2027, and negotiators have watched voluntary benchmarks turn into finance conditions before.
The reply is the difference between a stock and a rate. A single global figure for queued capacity, however often it is repeated, cannot show whether projects are clearing faster than last year, how many applications are abandoned, or who pays for reinforcement. A 2028 review needs a rate. A template assembled from disclosures operators already make standardizes reporting without creating new statistical obligations — and a clause stating the baseline cannot be used to condition finance answers the conditionality worry where it starts.
Four fields would do most of the work, and three of them are already public somewhere.
Two limits belong in the first edition. Distributed solar, storage and demand response increasingly connect at distribution level or behind the meter, so a transmission-only template describes a shrinking part of the system; the same counting gap already shows up in industrial heat, where a share target says nothing about which fuel was displaced. And publication can substitute for funding: a government can release a queue report and finance nothing.
Revision is the third limit. The 21% and 23% starting points show how quickly definitions move, so publish a series with stated methodology changes rather than one number that has to be defended.
The work starts now, because a stocktake concluding in 2028 will read documents drafted in 2027.
No. As presented by the presidency and described by outside analysts, it is a political target with a contested baseline. The queue annex argued for here is voluntary as well — that is its selling point and its weakness.
The IEA documents queue levels and investment needs, which is essential context. It does not hand you a market-by-market withdrawal rate or a published cost-allocation rule, and those two decide whether queued megawatts become operating assets.
Only if signatories let it. The design that survives is an annual annex with a named custodian, plus explicit language that the baseline cannot be used to gate finance.
The share of queued capacity holding a signed interconnection agreement or a committed upgrade budget. In the US data that analogue sat at about 18% of active capacity, roughly 408 GW — more informative about deliverability than any queue total.
A first edition published in 2027 would land before the stocktake's technical phase begins in the middle of that year, giving the review a document to work from and investors a way to compare markets. That takes an annex, a custodian and a date — no treaty, no new agency, no mandatory disclosure regime.
The open question is whether a pledge built to be quoted in communiqués survives being measured. Britain and the United States both learned that once an admission rate is public, someone asks why it is what it is. A metric honest enough to be useful turns out to be specific enough to be used against the governments that sign it — which is either the argument for attaching it, or the reason it will be postponed again.