PolicyAndRegulation Case Review: What Two Grid-Queue Reforms Teach COP31's 35x35 Pledge | MyTechDailyNews

In Antalya the COP31 presidency put a single figure on the screen — electricity at 35% of final energy use by 2035 — and the applause was for a number nobody in the room has agreed how to check. The short answer: the pledge counts a share, not a connection rate, and two live reforms in Britain and the United States already publish the indicators that would close the gap.

Both cases are useful for an unglamorous reason. Britain was forced to rank a queue it could no longer defend; the United States was forced to count withdrawals after a decade of speculative filings. Neither reform was written for a climate target, which is precisely why the mechanics travel.

What does 35x35 promise, and what does it leave uncounted?

Turkey's presidency wants electricity at 35% of the world's final energy use by 2035, and the accompanying text says nothing about how anyone would verify that the capacity behind the number actually connects. The pledge is a percentage, and percentages move without a single new line being energized.

Reporting from the opening session put electricity at 21% of end-use energy and cited a Rhodium Group projection of 28% by 2035. The World Benchmarking Alliance describes the proposal as a climb from roughly 23% of final energy consumption, and an independent COP31 analysis uses the same 23% starting point. Two percentage points looks like bookkeeping until you notice what it decides: who gets to claim success.

The boundary is the reason. End-use energy and final energy consumption cut the system in different places, and efficiency gains, fuel switching and international bunkers land on different sides of the line. Shift the convention and a government can report 35% built on a redefinition plus a decade of efficiency improvement while connecting almost nothing.

Even with the boundary fixed, the climb is steep. Rhodium's central path reaches 28%, so seven points have to be closed in ten years — requiring slow growth in final demand, fast scaling of clean generation, and networks that connect new supply and new load at a pace most systems have rarely managed. The first two show up in energy statistics; the third shows up in no headline indicator at all. And a share can also rise with no wire: trim final demand, hold electricity use steady, and the percentage climbs while the grid does nothing new.

Case one: how did Britain turn a 700 GW queue into a ranked pipeline?

Britain's answer was to stop treating the queue as a line and start treating it as a filter. First-come-first-served gave way to two tests — readiness and strategic alignment — with the criteria published so developers could argue with the scoring instead of with each other.

Ofgem issued its final decision on the connections reform package, TMO4+, on 15 April 2025, opening a 56-day licence standstill that ran to 10 June 2025 (Simmons & Simmons). Before the reform, NESO's connections publications described a GB transmission queue above 700 GW (NESO). Gate 2 then did the sorting: about 217 GW of Gate 2-ready capacity was not prioritised because it failed the strategic-alignment test, and the resulting pipeline landed at roughly 100 GW (Walker Morris).

Read that as a rate rather than a trophy. The purpose was never to shrink a queue; it was to generate an annual answer to "how many projects cleared the gate, and which ones were told to wait?" Ofgem has since consulted on a returnable commitment fee for large data-centre connection requests, aimed at deterring non-viable applicants (Ofgem consultation, July 2026).

The lesson for a COP annex is unglamorous: a regulator-approved methodology, published criteria and a scheduled re-ranking produce a comparable series. Britain's own electrification scorecard shows how far rules can run ahead of delivery, splitting 82% for enabling conditions against 38% for deployment.

Case two: what did the US change, and what appeared in the data afterwards?

The American reform attacked the study process itself, and the more useful legacy for COP31 is what became countable. FERC Order 2023 moved regional grids to cluster studies, tightened readiness requirements including a 90% site-control threshold, imposed withdrawal penalties and spread network-upgrade costs across clusters; the D.C. Circuit later upheld the package (RTO Insider).

Berkeley Lab's Queued Up series then produced the kind of figures a share target cannot: at the end of 2025, about 8,200 projects were seeking transmission interconnection, representing 1,312 GW of generation and roughly 749 GW of storage — just over 2,000 GW in total (Queued Up: 2026 Edition). The queue did not grow that year. Withdrawals of about 750 GW outran roughly 600 GW of new requests, and active volume fell around 10%.

Attrition is the variable worth staring at. The prior edition found 61% of active capacity — some 1,400 GW — carrying a proposed online date before 2028, while only 18%, about 408 GW, held a draft or executed interconnection agreement (Queued Up: 2025 Edition). Wait times have lengthened in parallel: the typical stretch from connection request to commercial operation rose from under two years for projects built in 2000-2007 to a median of five years for projects built in 2023 (Queued Up: 2024 Edition).

Look further back and the funnel narrows hard. Among requests filed between 2000 and 2018, just 19% of projects and 14% of capacity reached commercial operation by the end of 2023 (Berkeley Lab). Not one of these numbers needed a new statistical agency — they came from disclosures operators already file, cleaned and published on an annual cycle.

What do the two cases prove side by side?

They prove the yardstick is a design choice rather than a data impossibility, and they disagree about which end of the process to measure — which is why a pledge should borrow both.

DimensionBritain (TMO4+ / Gate 2)United States (Order 2023 + Queued Up)What a 35x35 annex should borrow
What the reform changedReadiness and strategic-alignment tests replace queue orderCluster studies, 90% site control, withdrawal penalties, shared upgrade costsRules that create comparable outcomes, not just faster processing
What gets publishedRegulator-approved criteria and methodology, plus a re-ranked pipelineAnnual project counts, megawatts, withdrawal volumes, share holding an agreementA fixed annual series with stable definitions
Visible resultQueue above 700 GW before reform; roughly 100 GW prioritised after Gate 2About 2,061 GW active at end-2025; roughly 750 GW withdrawn that yearStock and flow reported together
Transferable lessonAdmission rate per cycleSurvival rate and cost allocationQueue length, withdrawal rate, agreement share, upgrade-cost split

The last row is the one to carry into a negotiating room. Britain measures who gets in; the United States measures who survives. A pledge about capacity that actually runs needs both numbers for the same year.

Where the pledge still has no yardstick

The global total everyone quotes is a practitioner estimate, not a census — which is exactly the problem. Writing on LinkedIn, Alicia Argüello put more than 2,500 GW of renewable generation, storage and large-load projects waiting for connection worldwide (Alicia Argüello). Treat it as an order of magnitude; even at that strength it locates the bottleneck.

The IEA's Electricity 2026 assessment reports grid connection queues at record levels worldwide and calls for annual grid investment to rise sharply through 2030 to keep pace with demand (IEA). Neither that report nor the 2,500 GW figure gives a market-by-market withdrawal rate or a cost-allocation rule, and those are the variables where projects actually die.

Two structural gaps sit underneath. A diagnosis of China's distribution-grid reforms found that available capacity is now disclosed, but the mechanisms separating speculative queue positions from viable projects, the triggers that release held capacity and the principles for sharing upgrade costs still rest on administrative coordination rather than published rules (sdg-china.net) — the same pattern in a different power system. For Africa, the argument is framed around connections, cooking and who pays, with grid finance treated as the binding constraint ahead of the share itself (ESI Africa; ecoltdgroup).

Where the network was never built to reach a region, the queue is less a list of stalled projects than a list of projects nobody proposed. No indicator fixes that. A cost-allocation rule at least makes the bill visible.

Why some governments would rather not have a metric

The strongest objection is political, not technical: 35x35 is an instrument for moving finance, and a queue baseline over-specifies it. The Green Grids Initiative welcomed the target on roughly those grounds, crediting it with placing grids at the centre of the electrification agenda (Green Grids Initiative).

A sharper version comes from the countries the pledge is meant to help. Any indicator attached to a voluntary target can later be used as a test. The second global stocktake opens at this conference and is scheduled to conclude at COP33 in 2028, with technical work starting in mid-2027, and negotiators have watched voluntary benchmarks turn into finance conditions before.

The reply is the difference between a stock and a rate. A single global figure for queued capacity, however often it is repeated, cannot show whether projects are clearing faster than last year, how many applications are abandoned, or who pays for reinforcement. A 2028 review needs a rate. A template assembled from disclosures operators already make standardizes reporting without creating new statistical obligations — and a clause stating the baseline cannot be used to condition finance answers the conditionality worry where it starts.

What should the annex hold, and what should it refuse to become?

Four fields would do most of the work, and three of them are already public somewhere.

  • Queue length in projects and in megawatts — the stock, comparable across markets and years.
  • Withdrawal rate — separates speculative filings from serious ones, and cuts both ways: a large queue with heavy attrition may be clearing faster than its size suggests, while a stable queue may be one that has frozen new entrants out.
  • Upgrade-cost allocation — decides whether a project survives after it clears the gate.
  • Share of queued capacity holding a signed connection agreement or a committed upgrade budget — the indicator that makes publication hard to pass off as construction.

Two limits belong in the first edition. Distributed solar, storage and demand response increasingly connect at distribution level or behind the meter, so a transmission-only template describes a shrinking part of the system; the same counting gap already shows up in industrial heat, where a share target says nothing about which fuel was displaced. And publication can substitute for funding: a government can release a queue report and finance nothing.

Revision is the third limit. The 21% and 23% starting points show how quickly definitions move, so publish a series with stated methodology changes rather than one number that has to be defended.

What should compliance, strategy and investment teams do before 2028?

The work starts now, because a stocktake concluding in 2028 will read documents drafted in 2027.

  1. Baseline your own market. Pull the operator's queue dataset and record project count, megawatts, withdrawals and agreement status for three years. Most operators publish more than their national statistics office does.
  2. Track the rate. Ask what share of the queue cleared per study cycle rather than how big the queue is. A shrinking queue and a frozen queue look identical in a headline.
  3. Price the upgrade bill early. Cost allocation is where developments stop; model it before signing an agreement, not after studies land.
  4. Read the annex as a finance signal. If a 2027 baseline exists, lenders get a cross-market comparison that today lives mostly in paid consulting decks.
  5. Check the speculative/viable split for large loads. Data centres and electrolysers should treat an unseparated queue as a schedule risk in site selection.

FAQ

Does 35x35 legally bind countries to reach 35%?

No. As presented by the presidency and described by outside analysts, it is a political target with a contested baseline. The queue annex argued for here is voluntary as well — that is its selling point and its weakness.

Why not simply rely on the IEA's grid reporting?

The IEA documents queue levels and investment needs, which is essential context. It does not hand you a market-by-market withdrawal rate or a published cost-allocation rule, and those two decide whether queued megawatts become operating assets.

Would a queue metric become a condition on climate finance?

Only if signatories let it. The design that survives is an annual annex with a named custodian, plus explicit language that the baseline cannot be used to gate finance.

Which single number should a compliance team watch?

The share of queued capacity holding a signed interconnection agreement or a committed upgrade budget. In the US data that analogue sat at about 18% of active capacity, roughly 408 GW — more informative about deliverability than any queue total.

What to watch next

A first edition published in 2027 would land before the stocktake's technical phase begins in the middle of that year, giving the review a document to work from and investors a way to compare markets. That takes an annex, a custodian and a date — no treaty, no new agency, no mandatory disclosure regime.

The open question is whether a pledge built to be quoted in communiqués survives being measured. Britain and the United States both learned that once an admission rate is public, someone asks why it is what it is. A metric honest enough to be useful turns out to be specific enough to be used against the governments that sign it — which is either the argument for attaching it, or the reason it will be postponed again.

References

  • Grids - Electricity 2026 - IEA
  • Queued Up: 2026 Edition - Berkeley Lab
  • Queued Up: 2025 Edition (PDF) - Berkeley Lab
  • Queued Up: 2024 Edition - Berkeley Lab
  • Grid connection backlog grows 30% in 2023 - Berkeley Lab
  • Ofgem Approval of Grid Connection Queue Reform (TMO4+) - Simmons & Simmons
  • About Connections Reform - NESO
  • New connections delivery pipeline explained - Walker Morris
  • Proposed data centre connection reforms - Ofgem
  • D.C. Circuit upholds FERC Order 2023 - RTO Insider
  • COP31: We woke up to the grid challenge - Alicia Argüello
  • Powering the transition - World Benchmarking Alliance
  • Senate Moves Toward Procedural Vote as COP31 Opens - Green Carbon World
  • COP31's 35-by-35 Global Electrification Push - Down To Earth
  • 35% by 2035: Whose electrification is the COP31 pledge talking about? - ESI Africa
  • COP31: The 35-by-25 electrification pledge and the grid finance gap
  • China's reform agenda under COP31's 35x35 target
  • Green Grids Initiative welcomes 35x35 target for 2035

Related reading

  • AI data centres need penalty-backed grid-impact bonds
  • COP31's Nuclear Push Needs a Readiness Ledger for Fuel and Waste | MyTechDailyNews Policy and Regulation
Brand logo

Tech Daily

Your Daily Source for Consumer Tech, Policy & Communications

HardwarePolicy & RegulationSoftwareCommunicationsConsumer ElectronicsGeneralAPAC EdmGrowthAbout Us

© 2026 Tech Daily.

Cookie Notice

We use cookies to improve your experience and analyze website traffic. Read our Privacy Policy to learn more.