By Hugo Phillips · Carbon-neutrality consultant · Tech Daily · hello@techdaily.com
A project should not collect climate credit for steel and cement it cannot name. My working answer to the question this column keeps receiving from tender teams: a green construction claim becomes verifiable only when it publishes product-level environmental product declarations for the materials actually purchased, names the product category rules behind them, and sets emissions thresholds before bids are scored. Until those three items exist, the claim is narrative, not evidence.
The question is not hypothetical for me. I have sat through enough bid openings to recognize the pattern: a persuasive sustainability chapter, efficient equipment schedules, a certification target — and then a bill of quantities where steel and cement arrive on paperwork that says little about the specific products inside the beams. The emissions profile of those materials is largely locked in at specification and purchase, long before the building generates an operating record. If the record stops at the gate of the procurement office, everything downstream is interpretation.
Mostly systems and intentions — not materials. Sustainability chapters describe recycled content, durability and a certification route, while the embedded-carbon decisions with the largest single impact pass through with averages instead of product data. The public record supports that skepticism. A GMCA framework states that cement and concrete are responsible for approximately 8% of global greenhouse gas emissions. An NRDC article finds that concrete products often calculate cement emissions using industry averages rather than actual cement product carbon data, which blunts the force of green procurement. The World Resources Institute notes that the main product-level procurement initiatives for cement and steel come with varying definitions of the regulated material — so even motivated buyers can be comparing different things under the same label.
The comparability problem has a known infrastructure fix, and regulators already lean on it. Type III environmental product declarations built to ISO 14025 require independent verification, and EN 15804+A2 supplies the core product category rules for construction products — the mechanism that makes two rebar declarations comparable rather than merely similar in tone, as the EPD International primer at environdec.com explains. The market already has the instrument a contract needs; the gap is that most green claims simply do not demand it. One operational observation from my own beat: the sequencing question here is not unique to cement. The EU battery health mandate debate follows the same logic — data captured at the product layer determines whether downstream buyers can price what they are buying, as argued in our earlier piece on the pack-level battery health record (why pack-level records beat cell readouts).
Because data that never enters the contract cannot change what gets bought. An environmental product declaration tied to the relevant product category rules gives a buyer a named basis for comparison, and a cement and concrete procurement guide notes that EPDs using relevant PCRs can be written into contracts. Steel or cement that looks identical on a drawing can carry materially different emissions depending on process, electricity, feedstock and plant controls. Terms need tight handling too: Scope One covers direct fuel use controlled by the reporting company, Scope Two covers purchased energy, and Scope Three — where purchased steel and cement usually sit — covers value-chain emissions. CCER, Chinese Certified Emission Reduction credits, belongs in a separate ledger from the physical emissions in a beam or a bag of cement; credits can fund mitigation elsewhere and leave embodied carbon unchanged. Keeping offsets out of the materials account echoes the argument our column made about buffer accounts buyers cannot read in the Article 6.4 discussion (buffer ledger reversal risk).
Regulation is converging on the same demand from the import side. The EU Carbon Border Adjustment Mechanism entered its definitive regime on 1 January 2026, obliging importers of cement, iron and steel, aluminium, fertilisers, electricity and hydrogen to report embedded emissions and, from the first surrender deadline of 30 September 2027, pay for them. CBAM accepts actual production data or default values, and default values are designed to cost more — the same conservative-placeholder logic I would apply to a project missing an EPD. When embedded product data becomes a customs liability on one continent, treating it as decoration in green claims elsewhere looks increasingly untenable.
There is also commercial evidence that product-level data pays for itself. Dassault Systèmes company material reports 173t of avoided steel production and 264.844tCO2e avoided in a construction case, and notes that emerging product-level emissions standards require verifiable lifecycle data, with the same underlying data point feeding both the ESG report and the cost analysis. I treat those results as indicative, not sector-wide proof — a mechanism demonstration, not an average outcome. The mechanism matters: once product data sit beside the bill of quantities, engineers and cost managers can see whether a specification change affects carbon or only appearance, and a green premium becomes a priceable line item at the moment a bid is accepted.
Shorter than you would expect, and testable without waiting for a global standard:
None of this is theoretical. California's Buy Clean California Act already runs the pattern on public works: bidders submit EPDs for covered materials, and the state sets maximum global warming potential limits rather than asking for effort. Under the updated schedule effective 1 January 2025, unfabricated concrete reinforcing steel caps at 755 kgCO2e and fabricated product at 778 kgCO2e. The program even carries a phased carve-out — no EPD required where a covered product's total material cost falls below $25,000 — which is precisely the wide-evidence, firm-threshold, small-purchase-exempted design that answers the exclusion objection before it is raised.
The paperwork is real; misbuying costs more. Anyone who has collected supplier emissions data knows the friction: mills and concrete producers sit in different declaration programs, product category rules, allocation methods and data boundaries; procurement teams hold price and delivery while sustainability teams hold carbon spreadsheets, and many firms stall at Scope Three because supplier data are uneven. A hard EPD-only rule could favour large suppliers with dedicated sustainability teams, exclude smaller plants holding credible but less polished data, and create false precision where plant boundaries or allocation choices differ. GMCA's framework shows the sector is still settling attribution methods such as book and claim, and procurement guidance flags mass balance as an open accounting issue.
The workable response is a phased rule: accept equivalent verified product data where an EPD is not yet available, publish the product category rules behind each comparison, give smaller suppliers a clock to meet the requirement, and surface exceptions publicly. That preserves the threshold's teeth while cutting the exclusion risk. My honest scorecard after watching both approaches in the field: strict-with-carve-outs beats voluntary-every-time, because voluntary regimes select for marketing departments rather than for low-carbon mills.
Public buyers, by a wide margin. Research on green public procurement in China estimates that around one-third of total annual steel and cement demand in China is used for public construction, and European procurement research estimates a lead market for low-carbon cement at 31% of the total EU cement market. Official statistics also show material markets can be described in fine detail — GOV.UK's construction materials commentary for June 2026 publishes data on selected materials including cement and concrete reinforcing bars, which is exactly the level of traceability climate claims should match. Put the three levers side by side:
| Lever | What triggers it | Data required | Threshold mechanics | Key date |
|---|---|---|---|---|
| EU CBAM definitive regime | Importing covered goods into the EU | Actual embedded emissions or default values | Default values penalise data gaps financially | Regime live 1 Jan 2026; first surrender 30 Sep 2027 |
| Buy Clean California Act | Bidding on California public works | EPD for covered materials | Maximum GWP caps; sub-$25,000 purchases exempt | Updated rebar limits from 1 Jan 2025 |
| ISO 14025 / EN 15804 route | Contract clause set by the project owner | Independently verified Type III EPD under a named PCR | Owner-defined emissions intensity per category | Adoptable in the next tender cycle |
The caution these figures leave is buyer readiness: scale does not guarantee that procurement offices can read an EPD, and capability building belongs on the same timeline as the clause itself.
No. An EPD is a verified disclosure, not a pass mark. It becomes procurement-relevant only when a threshold is attached; without the cap, it is measurement without consequence.
Accept equivalent verified data temporarily, publish a conservative proxy, and write a contractual deadline for replacement declarations. Until the data arrive, the project should not count the climate benefit.
No. CCER or other credits sit in a separate account from the physical emissions in the product. They can fund mitigation elsewhere; the beam's embodied carbon stays what it is.
The clause is contract law, so any owner can adopt it today; public buyers simply carry the most demand-side weight, given the volumes cited above.
Yes — on the next tender, not the next strategy cycle. My recommendation in one pass: separate the claim boundary, attach product-level EPDs with named product category rules for the steel and cement actually bought, set the emissions threshold before scoring, and count the benefit only once disclosures, thresholds and exceptions survive review. A project that publishes its thresholds and exceptions may look less polished at launch; it will age better, because when auditors or regulators ask how the material claim was built, the answer already sits in documents created during procurement. If your team wants a second opinion on clause language, our desk reads tender files at hello@techdaily.com. — Hugo Phillips, Tech Daily