Brand logo
HomeHardwarePolicy & RegulationSoftwareCommunicationsConsumer ElectronicsGeneralAbout Us
  1. Home
  2. /
  3. policyandregulation
  4. /
  5. rhodium-baaja-permitting-emissions-costs-2040

Case Review: What SunZia's Permit Marathon and Virginia's Big-Load Tariff Teach About the Senate Permitting Bill

By Sarah Chen — Tech Daily, Policy and Regulation desk · Editorial contact: hello@techdaily.com

Two live case files answer most of what the Senate's bipartisan permitting package actually does. A 550-mile transmission line spent roughly 17 years chasing approvals before it could be built; a state utility regulator rewrote tariffs so that data centers pay for the grid capacity they consume. Read together, they show that the bill changes approval speed, legal exposure and cost allocation — not clean-energy funding. The climate dividend that follows is real, but the Rhodium Group calls it modest.

On September 30, 2026, Senators Shelley Moore Capito (R-W.Va.), Mike Lee (R-Utah), Sheldon Whitehouse (D-R.I.) and Martin Heinrich (D-N.M.) introduced S. 5653, the 417-page Bipartisan American Affordability and Jobs Act, or BAAJA, according to committee press releases on senate.gov. Engineering News-Reporting reported that Senate leaders were teeing up a floor vote after the November 2026 midterms. For managers, developers and compliance counsel, the useful question is not whether the text passes, but what its clauses do to a project lifecycle. That is where the cases pay off.

What does the Rhodium Group analysis actually measure?

Conclusion first: it prices the second-order effects of a build-speed law, and it refuses to call them a climate plan. The independent research firm modelled the BAAJA provisions with the clearest effect on climate pollution and the energy system, and found a likely slight decline in greenhouse gas emissions plus lower electricity bills by 2040 versus current policy. Under the worst-case reading, emissions are not pushed up; they simply stay on the trajectory they are on today.

Set against status-quo policy, the best case cuts U.S. economy-wide emissions by 4%, lowers household energy bills by $78 per year, and supports more than 200 gigawatts of new clean energy capacity by 2040. In the worst case, greenhouse gas emissions hold their current path.

Ben King, an energy and climate director at Rhodium, insists the output be read as directional guidance rather than an exact accounting. King said: “We don’t see emissions increasing because of the bill,” and added: “This bill should drive some emission reductions, it should drive some more clean energy on the grid, and it should drive electricity bills down. And given the complexity of the bill, that’s what we can say at this point.”

Why the hedging? BAAJA mixes incentives, so its effects pull against each other. Easier approval makes long-distance transmission cheaper to build and faster to construct; the same assumption is applied to gas pipelines, which expand fossil output. Recent partisan measures — the Inflation Reduction Act that Joe Biden signed in 2022, or President Trump's tax and spending bill — were analyzable because their incentives ran in one direction. Here they do not.

Case 1: How did a 550-mile transmission line need 17 years of permits?

SunZia Southwest Transmission is the textbook. The line is designed to move roughly 3,500 megawatts across New Mexico, and its permitting trail began in the mid-2000s: developers sought federal approval in 2008, the Obama administration designated it a fast-track project four years later, the Bureau of Land Management approved the right-of-way in 2015, and final federal environmental review and authorization landed only in 2023, as documented on the federal permitting site permits.performance.gov. Energy Daily's reporting put the arithmetic bluntly — about six years to build, seventeen years to permit.

That single project explains the bill's central climate claim better than any chart. Rhodium found that BAAJA could nearly triple the build rate of high-voltage transmission, moving from an average of about 0.7 terawatt-miles added per year over the past decade to an average annual pace of 1.9 to 2.6 terawatt-miles through 2040.

The empirical record behind that gap is uncomfortable for anyone planning a project. A CATF case-study database of large U.S. lines (over 100 miles and above 345 kV) found the average interval from notice of intent to a signed record of decision was 4.7 years among the 17 lines that were not cancelled. Grid-build advocates at cleanenergygrid.org reported that only 322 miles of high-voltage line were completed in 2024 — the third slowest year of the last 15. Note the unit mismatch: those are route miles, while Rhodium's terawatt-miles weight distance by capacity, so the two series measure different things and should not be averaged together in an internal model.

Why transmission speed is treated as climate policy at all goes back to Princeton University. After the Inflation Reduction Act passed in 2022, its researchers concluded that slow line construction would be a major obstacle to realizing the law's benefits: unless the country more than doubled the rate of transmission expansion, more than 80% of the IRA's emission reduction potential by 2030 would be lost. Because Republicans and President Trump have repealed many IRA provisions, BAAJA will not deliver the volume of clean energy those researchers anticipated; Rhodium still estimates that by 2040 it helps between 17 and 249 gigawatts of clean resources get built compared with a world without it.

Reusable lesson for project teams: the binding constraint on SunZia was never capital or hardware. It was the durability of an approval. Clauses that compress review deadlines and narrow judicial remedies therefore change a developer's risk register even where the emissions math looks marginal.

Case 2: What does Virginia's big-load tariff foreshadow for BAAJA's cost rules?

The expanding grid is the main reason the bill lowers energy costs, because it lets cheaper resources connect. The second lever is cost allocation: the bill requires data centers to pay the full cost of connecting, which puts downward pressure on electricity rates.

States got there first. Virginia's State Corporation Commission approved a new rate class aimed at the biggest electricity users, taking effect January 1, 2027, after Dominion Energy sought multi-year commitments from very large customers — a policy fight driven by Northern Virginia's data-center density. The market backdrop is visible in prices: a Maryland Office of People's Counsel study with Synapse found PJM capacity clearing prices jumped from $49.49 per megawatt-day in 2024/2025 to $269.92 for 2025/2026, and EIA's September 2026 Short-Term Energy Outlook projected wholesale prices in the PJM region rising 41%. Third Way's November 2026 polling memo put lowering utility bills (62%) and keeping the power on (57%) as voters' top energy priorities. That is the political fuel under BAAJA.

Now port that case onto the federal text. Rhodium estimates BAAJA's ratepayer protection provisions make connection roughly 10% more expensive for a 1 gigawatt data center. Legal analysts at JD Supra note the bill would direct FERC to revise transmission pricing policy for high-density computing loads within 270 days of enactment, and the Bipartisan Policy Center's explainer adds that the design asks data centers to cover both their share of the existing system and the new cost they trigger, with a discount for those accepting interruptible service.

Demand assumptions are where the two cases collide. Rhodium's base case has data centers accounting for about 17% of electricity demand by 2040 — already a very large jump, because they use only about 5% of U.S. electricity today. To probe a faster ramp, the authors ran two additional scenarios in which data-center demand would instead take more than a quarter of U.S. electricity in 2040. And because whether those costs push developers on-grid or off-grid was outside the scope, the modellers examined two extremes: all additional demand connecting to the grid, and none of it doing so. Their finding is the one to brief a CFO on: even if most new demand were served by grid-connected gas plants, emissions would still be 30% lower than if the same demand were met by inefficient off-grid gas plants.

Reusable lesson: a connection surcharge is not automatically a deterrent. In the on-grid scenario, whether additional demand lands on gas plants or cleaner sources depends largely on the price of fossil generation compared with clean generation.

Why do the emissions numbers look small — and where is the legal risk?

Because BAAJA is not a climate bill. It is not designed to reduce fossil fuel dependence or advance clean energy technologies; its purpose is to relieve federal bottlenecks that slow America's ability to build infrastructure, whether a pipeline, a highway, a power line or a solar farm. A limited emissions impact is unsurprising.

Senate climate champions still treat it as a priority, because several provisions are precursors to faster decarbonization. King framed it that way: “If your goal is to do climate policy in the future, this is an important down payment to making progress there.”

The pipeline side runs the other way. Changes to the Clean Water Act and the National Environmental Policy Act would enable more gas pipeline development, and taken alone that raises emissions versus a world without BAAJA, since more pipelines mean more oil and gas production and higher methane and CO2 across the fossil supply chain. At the worst, Rhodium estimates a 4% increase in new gas capacity, although gas-fired generation as a whole increases by less than 1% in 2040 — and even then emissions stay flat against current expectations. King's summary: “On net, the emissions increases that we see there are outweighed by the emissions benefits that come from the transmission provisions of the bill.”

It is the second analysis to reach a comparable verdict. A narrower report covering only the power grid, published last week by the think tank Resources for the Future, found the legislation could cut electricity emissions by 6% and reduce electricity system costs by $350 billion through 2050.

Caveats matter more here than in most modelling work, because they cluster on both sides. The analysis excluded the bill's permitting-certainty provisions — which Democrats initially sought in order to stop President Trump's war on wind and which have become one of its thorniest sections. Rhodium's model is also a rough instrument for transmission policy: it weighs economic inputs such as supply and demand rather than the physical layout of the U.S. grid, including where lines run or where bottlenecks appear. Geothermal support, virtual power plants, advanced transmission technologies and the bill's potential to cut grid congestion were all left out, and each could lower emissions further. Conversely, the model assumes that all data centers built between now and 2040 connect to the grid, which likely underestimates emissions from the off-grid plants being planned today. The authors also performed a separate exercise that examined data centers more deeply. Scope was limited to the United States: even though the modelling found liquified natural gas exports would increase by 8% to 15% under BAAJA, the effect of those exports on the energy mix or emissions elsewhere was not assessed.

Compliance and litigation risk sits in the process clauses, not the energy maths. Summaries from Rhodium, the Institute for the Freedom of the Planet and law-firm alerts describe a narrowed definition of "major federal action" under NEPA, review deadlines beyond those in the 2023 fiscal reconciliation act, altered standing, a 150-day statute of limitations for certain NEPA challenges, and remand without vacatur as the main remedy. The Bipartisan Policy Center notes a completed NEPA review can otherwise be challenged for up to six years under the Administrative Procedure Act's default limit. Earthjustice's 2026 impact guide argues section 1110 sweeps in claims seeking judicial review under other federal law — the core objection from opponents, and the reason a passed bill may still be tested in court for years.

How do the competing readings of the same bill differ?

ReadingScopeEmissions signalCost signalHorizonBlind spot for planners
Rhodium Group, full-system modelTransmission plus gas-pipeline permitting provisionsBest case: 4% below status quo; worst case: flat$78 per year off household energy bills2040No physical grid layout, no certainty provisions, no offshore effects
Resources for the Future, power-grid onlyGrid provisions aloneElectricity emissions down 6%System costs down $350 billion2050Excludes pipeline-driven upstream emissions
Empirical permitting record (CATF case database; SunZia)Observed federal review timelinesNot modelledNot modelled2005-2024Cannot price the effect of new statutory deadlines

What should developers, operators and counsel do in the next 12 months?

  • Re-time the filing calendar. Map every project in the pipeline against the 150-day challenge window and the new review deadlines; the value of a permit now depends heavily on when the clock starts.
  • Re-underwrite the "permit durability" assumption. SunZia's 17-year exposure was a sequencing risk, not a financing risk. Update board risk registers to separate approval speed from approval survival.
  • Model on-grid versus off-grid twice. Run a gas-price-collapsed case and a clean-energy-cheap case, mirroring Rhodium's bookends; the 30% differential is the number that changes siting decisions.
  • Budget for the connection surcharge. Treat the roughly 10% cost uplift for a 1 gigawatt load as a base-case input, and watch FERC's pricing proceeding inside the 270-day window for the rule that fixes it.
  • Track Virginia as the template. A rate class effective January 1, 2027 gives state-by-state precedent that federal rules may absorb, so multi-state operators should assume cost-allocation divergence continues.
  • Prepare for litigation either way. Environmental groups have flagged the judicial-review language, so a favorable bill outcome is a starting gun for court tests rather than an all-clear.

FAQ: the first questions a compliance team asks

Does BAAJA increase U.S. emissions?

No, on Rhodium's reading. In the worst case emissions remain on today's path; the pipeline provisions push them up, and the transmission provisions outweigh that on net.

Why is the climate impact framed as modest?

Because the legislation targets federal bottlenecks across all infrastructure. It has no decarbonization mandate, and many IRA provisions have been repealed, so the clean-energy gain lands between 17 and 249 gigawatts rather than the larger buildout Princeton University had projected.

Who pays for data-center grid connections?

The bill pushes the cost onto large loads, raising connection expense by roughly 10% for a 1 gigawatt facility, and directs FERC to set the pricing rule within 270 days of enactment.

Is the modelling an endorsement?

No. Ben King describes the results as directional. The certainty provisions, physical bottlenecks, geothermal, virtual power plants and export effects are all outside the model, so treat the ranges as planning signals, not audit-ready figures.

Sources referenced

  • Rhodium Group, "Estimating the US Energy System Impacts of the Bipartisan American Affordability and Jobs Act" — https://rhg.com/research/baaja-us-energy-system-impacts/
  • U.S. Senate Energy & Natural Resources and EPW committee releases on S. 5653 — https://www.energy.senate.gov/press/dem/heinrich-lee-capito-and-whitehouse-introduce-bipartisan-american-affordability-and-jobs-act-of-2026/
  • CRS product on BAAJA (S. 5653) — https://www.congress.gov/crs-product/R49492
  • Federal permitting fast-track record on SunZia — https://www.permits.performance.gov/fpisc-content/billion-dollar-transmission-line-project-breaks-ground-after-receiving-permitting
  • Council for American Abundance / CATF, "Evidence-based recommendations for overcoming barriers to federal transmission permitting" — https://www.catf.us/wp-content/uploads/2024/04/evidence-based-recommendations-overcoming-barriers-federal-transmission-permitting.pdf
  • Clean energy grid reporting on 2024 line completions — https://cleanenergygrid.org/new-report-reveals-u-s-transmission-buildout-lagging-far-behind-national-needs/
  • Bipartisan Policy Center, explainer on the Senate permitting bill and on NEPA judicial review — https://bipartisanpolicy.org/explainer/explaining-the-senate-permitting-bill-the-bipartisan-american-affordability-and-jobs-act/
  • JD Supra analysis of BAAJA transmission pricing and FERC deadlines — https://www.jdsupra.com/legalnews/senate-unveils-bipartisan-permitting-1274893/
  • Maryland Office of People's Counsel / Synapse, PJM capacity price analysis — https://opc-dc.gov/wp-content/uploads/2025/05/PJM-Capacity-Market-Report-FINAL-OPC-Synapse.pdf
  • EIA Short-Term Energy Outlook — https://www.eia.gov/outlooks/steo/pdf/steo_full.pdf
  • Third Way polling memo on permitting reform — https://www.thirdway.org/memo/polling-americans-want-permitting-reform.pdf
  • Earthjustice impact guide to BAAJA — https://earthjustice.org/feature/bipartisan-american-affordability-and-jobs-act-2026-impact-guide
Brand logo

Tech Daily

Your Daily Source for Consumer Tech, Policy & Communications

HardwarePolicy & RegulationSoftwareCommunicationsConsumer ElectronicsGeneralAPAC EdmGrowthAbout Us

© 2026 Tech Daily.

Cookie Notice

We use cookies to improve your experience and analyze website traffic. Read our Privacy Policy to learn more.