For developers, lenders and public funders, the short answer is: a major HVDC corridor should publish congestion cost allocation, curtailment recovery and availability guarantee rules before commercial operation. The engineering award may be public; the settlement logic is what determines whether a renewable link is a bankable capacity asset or a decade-long dispute.
This MyTechDailyNews Policy & Regulation comparison is deliberately narrow. It asks where early disclosure reduces financing risk, where it can freeze an incomplete answer, and which rules developers should model before signing hedges, requesting public support or approving a corridor tariff.
The argument starts with a balance-sheet fact: an HVDC link is a capacity asset, and its settlement logic can shape revenue for a decade. The first dispute can arrive when the current first flows. That does not mean every project needs a public rulebook before energization.
It is wrong when the link is small, radial, controlled by one system operator, and used by no party that could be harmed after energization. It is also wrong when a central operator already publishes audited settlement rules with enough detail for developers and public funders to model the outcome before launch.
Where those exceptions do not apply, the asymmetry is material. The engineering record is public, while the settlement record often is not. PowerGrid Corporation of India Limited selected GE Vernova to build a 6 GW ±800 kV HVDC link from Barmer, Rajasthan, to South Kalamb for renewable delivery. The scope includes a bipolar arrangement of 2 times 3000 MW, new converter stations, supply of major equipment, site erection, testing, commissioning, the eLumina control system, and LCC valves made at Pallavaram. The award is dated to the fourth quarter of 2026.
That record is solid and is the part that generates press releases. It still does not answer what a developer, lender or public agency needs before signing: who pays when the path becomes scarce, who bears the cost when renewable output is ordered down, and what happens to revenue when availability falls short. A converter station transfers energy. A corridor transfers obligations. Those obligations are easier to design before commissioning than to settle after a dispute.
Congestion is moving from a network symptom to an operating bill, and the bill needs an owner. In the United States, transmission congestion costs were estimated to exceed 17 billion dollars in 2025, up from 12 billion dollars in 2024. A corridor developer cannot choose a hedging posture, a contract volume, or a request for public support without knowing how that congestion bill will be assigned.
Centralized optimization can reduce visible congestion. A summary of Chinese grid operation states that annual average congestion duration on 500 kV and above lines fell 43 percent in 2020, while the number of cross section flow exceedances fell 68 percent. The same summary records the tension in allocation methods. Nodal pricing supporters can invoke the principle that the party causing congestion should bear it, while users may find price signals hard to interpret when they do not map cleanly to observed grid conditions.
A cross-border comparison makes the exposure less local. ACER’s 2024 cross-zonal monitoring report states that the cost of managing congestion in the EU reached EUR 4 billion in 2023. ACER cross-zonal monitoring. The same region also supplies a legal anchor that investors already know: Commission Regulation (EU) 2016/1447 of 26 August 2016 sets requirements for grid connection of high voltage direct current systems and DC-connected power park modules. EUR-Lex. Those are not proof that every corridor needs the same settlement model; they are evidence that technical compliance and congestion cost can be separated from tariff politics long before energization.
The method matters. Centralized optimization can lower visible congestion yet still spread costs in forms that market participants do not see as prices. A corridor that publishes a fixed toll may look simple and still leave the decisive logic buried. Publishing the allocation formula early changes that. It lets participants test caps, floors, settlement intervals, and uplift treatment before they have signed long term contracts.
The congestion number and the curtailment number describe different pockets of risk. The 2025 Grid Strategies report places United States congestion cost above 17 billion dollars. A separate market monitoring note says PJM Interconnection does not reliably report curtailment figures. S&P Global Market Intelligence. That reporting gap matters because curtailment compensation rests on a factual chain.
The operator must say how forced curtailment is separated from economic curtailment, how the dispatch order is recorded, how the generator documents lost production, and how fuel cost, opportunity cost, or contract adjustment enters the settlement. Public funders and ratepayers need to pay compensation without creating a windfall for a plant that would have produced less anyway. A corridor built to integrate renewables should state that chain before commercial operation. The method can be conservative. The default should be published.
The Chinese Yunxiao example shows how fixed capacity pricing can miss peak value. A Tencent News report says the link had a fixed annual capacity charge of 230 million yuan, shared half by Fujian and half by Guangdong, and a fixed toll of 0.0256 yuan per kilowatt hour for other market participants. It says Guangdong load reached historical highs three times in June and became the first province to exceed 170 gigawatts, while the fixed toll did not capture that scarcity. Tencent News. The report is a media account, so policy detail needs confirmation by the operator. The direction is familiar: a flat toll can hide scarcity when peak demand, renewable output, and outages collide — a design trade-off examined in Verified Flexibility Credits vs. Flat Grid-Fee Breaks.
Forecast numbers show that capital is forming around HVDC before operating rules mature. One market report projects the HVDC transmission systems market rising from 13.4 billion dollars in 2026 to 19.0 billion dollars by 2033 at a 5.1 percent compound annual growth rate. Another projects the market from 14.01 billion dollars in 2024 to 22.07 billion dollars by 2030 at 7.2 percent. These are scenario markers. Persistence Market Research; MarketsandMarkets.
Supply chain pressure turns that scenario into project risk. A grid and cable investment review says HVDC cable prices rose 50 percent in a period and delivery lead times tripled. Energy transition cable review. If lead times lengthen, a converter station outage, transformer repair, or valve failure can become a long commercial argument. An availability guarantee without categories for forced outage, planned outage, partial derate, weather, fuel delivery, grid instruction, and market curtailment is a marketing term. It can promise a headline rate without saying which events count against it. A developer needs to know whether the guarantee responds to hardware failure, control system downtime, curtailment instruction, or third party work. The categories decide the bill.
The comparison below is not a scorecard of legal quality. It shows what each market model emphasizes, and where a cross-border investor may face a blind spot between public data and revenue risk.
| Model | Public anchor | Settlement blind spot | Decision use |
|---|---|---|---|
| India / PGCIL | Large EPC scope, converter stations, testing, commissioning and control system disclosed | Congestion cost, curtailment and availability consequences may not be visible to users | Use for asset-scale benchmarking, not for hedge design |
| United States | Congestion cost estimates and market monitoring notes | Curtailment reporting can be incomplete where price signals dominate | Useful for testing uplift, nodal exposure and contract caps |
| China | Centralized optimization and congestion-duration improvements reported | Fixed tolls may hide scarcity when peak demand and renewable flows collide | Useful for capacity-charge sensitivity and peak-value stress cases |
| European Union | HVDC connection requirements under Regulation (EU) 2016/1447; ACER congestion-cost monitoring | Technical compliance does not by itself define who recovers redispatch or curtailment costs | Useful as a template for separating engineering obligations from settlement rules |
The strongest counterargument supports transparency but warns that early rulebooks can harden uncertainty. HVDC corridors operate inside AC grids, renewable buildout, and market conventions that can change before the first long settlement cycle closes. A corridor operator cannot know how nearby transmission upgrades, renewable siting, regional market software, or settlement rules will shape flows in later years. A formula written before energization could lock the project into an outcome that later looks too generous to generators, too harsh to consumers, or too difficult for regulators to audit.
ACORE says United States HVDC deployment lags because of barriers and offers nine recommendations, a sign that governance gaps are real. ACORE. The U.S. permitting debate overlaps with a Policy & Regulation review of BAAJA's Grid Chapter, Compared, where planning, permitting and cost rules are separated to test what actually moves project timelines.
That risk is strongest when the corridor is a regulated asset with no third party access and a simple cost recovery path. In that setting, a basic tariff before commercial operation may be enough, and congestion formulas can be handled in a later regulatory case. It is also strongest when a system operator needs room to change dispatch practice without triggering compensation claims from multiple users.
The answer is not to remove rules; it is to mark them as provisional. The corridor can publish a default algorithm, a sample settlement sheet, a curtailment formula, and an availability schedule, with a stated recalibration period. That gives developers a starting model and preserves engineering discretion. If rules are absent, participants do not avoid rigidity. They wait for the first loss and then argue about which rule applied.
At minimum, a corridor operator should publish congestion cost allocation by hour or by the shortest settlement interval available in the local market. The method should say whether congestion is priced at the node, through a post dispatch uplift, by a zonal charge, or by a centralized optimization penalty. The document should include worked examples for normal demand, peak demand, and low demand. It should also say whether a third party may request a settlement calculation and how quickly the operator must answer.
Public funders need the same data. Taxpayers, utilities, and lenders may finance grid resilience. They often see milestone reports and then lose sight of settlement outcomes. A regular availability and curtailment report lets them distinguish technical underperformance from market design failure. The remedy then follows the diagnosis. One failure calls for engineering work. Another calls for a tariff review.
The argument should stop at the edge of the case. A small radial link, owned by one regulated utility and used only to export one renewable portfolio under a simple contract, can be handled inside the utility rate case. Curtailment can be handled inside the dispatch instruction. A published rulebook might add cost without adding information. The same applies where a central system operator already has audited settlement and transparent after the fact cost allocation, even if the initial document is short.
The proposal becomes necessary when multiple users share the path, public funding enters the project, or merchant renewable export depends on scarce capacity. In that situation, the corridor becomes a capacity instrument in someone else's dispatch. It should publish settlement rules before energization so developers and public funders are not learning them from invoices. A moderate rulebook is not a substitute for engineering judgment; it is the document that lets finance, law and dispatch speak the same language before the first current flows.
No. The case is strongest for shared corridors, publicly funded corridors and merchant renewable export paths. A single-user radial utility link may be adequately handled in a rate case or dispatch instruction.
Not a full tariff manual. A default congestion allocation formula, one sample settlement sheet, a curtailment accounting method and a provisional availability schedule are enough for a lender model.
Congestion is a market-level bill; curtailment is a project-level claim. Without forced-versus-economic classification, dispatch logs, metering rules and compensation formulas, a developer cannot know whether a shutdown instruction is recoverable revenue or a sunk loss.
No. Regulation (EU) 2016/1447 of 26 August 2016 sets technical grid-connection obligations. It is useful because it separates equipment requirements from commercial rules, showing that investors can require both without confusing them.