COP31 Nuclear Delivery Test: Does a Public Overrun Register Lower Costs or Raise Them? | MyTechDailyNews Policy & Regulation

Antalya’s summit floor is stacked with reactor pledges, so the only question left is whether any of those plants can be finished on budget. Short answer: yes, publish a register of construction cost and schedule deviations covering every generation technology, large reactors included alongside small modular designs — but design it to lower the cost of finishing a project, not the cost of ordering the first one. Get that wrong and the instrument makes the very problem it is meant to expose worse.

What did COP31 actually put on the table?

COP31 opened this morning in Antalya, and the host country’s flagship proposal is the 35x35 pledge: electrify 35% of the world’s final energy use by 2035. That is a build-rate target wearing a climate label. Electricity carries 21% of end-use energy today, and the Rhodium Group projects 28% by 2035, so the pledge asks the power sector to add roughly a third more share in a decade than current trends deliver — and to finish what it starts.

The politics moved faster than the plumbing. The World Resources Institute recorded that a group of countries endorsed the pledge at the Leaders’ Summit on 11 November 2026, which takes it out of a Presidency slide deck and into national planning documents, where it will eventually be audited against something. Note how the Presidency’s own launch material describes today’s starting point as “just over 20%” rather than 21% — a rounding, harmless on its own, and exactly the kind of drift that later becomes an argument about whether a target was met. The pledge also leaves an open question the drafters will have to answer: whether the industrial-heat gap in the 35x35 pledge gets a reporting line of its own, because an electrification share can climb while process heat stays stubbornly fossil.

Why does delivery, not doctrine, now decide the nuclear argument?

Because the pipeline is already big enough to test the industry. The IEA’s executive director, Fatih Birol, said in March that about 70 GW of nuclear capacity was under construction worldwide, the highest figure in 40 years. That number is the strongest thing nuclear has going for it, and it is also why the next question is unavoidable: 70 GW under construction is a promise, and promises get judged at commissioning.

Two constraints sit alongside it. The IEA estimates that annual grid investment of roughly $400 billion needs to rise by about 50% by 2030 to carry the electricity a higher-reliability system would produce, and it puts the total net-zero energy infrastructure bill to 2050 above $100 trillion. Every dollar of that has an alternative use, and the alternatives are getting faster. Anthropic’s $3.4 billion agreement for 1.7 GW of gas-fired engines bought equipment that can be delivered sooner than a reactor can be licensed — that is the competitive benchmark, whether or not anyone in the industry likes it.

Timing sharpens the point. The IEA expects data centre electricity demand to double by 2030, and reactors ordered now would not be running by then. Recent projects in the United Kingdom, France and Finland have all run past their budgets and their schedules. If nuclear is part of the answer to 35x35, the industry has to be able to show which projects went wrong, by how much, and why — in a record a lender, a regulator or a reporter can actually check.

How bad is the overrun record, really?

Worse than any other infrastructure category in the largest comparable dataset we have. The Boston University Global Sustainability Institute study of 662 energy infrastructure projects in 83 countries, spanning 1936 to 2024 and $1.358 trillion of investment, found that more than 60% exceeded their planned construction cost. Nuclear was the worst category on the authors’ own measure: the average plant overran by 102.5%, ending up $1.56 billion above its expected cost.

TechnologyAverage construction cost overrun
Nuclear102.5%
Hydropower36.7%
Geothermal20.7%
Carbon capture and storage14.9%
Bioenergy10.7%

What makes that figure usable is the company it keeps. The study modelled plants above 1 MW and transmission lines above 10 kilometres across coal, gas, nuclear, hydro, wind, solar, hydrogen and carbon capture, so nuclear is compared with the whole infrastructure menu rather than with a hand-picked set of the hardest reactors ever attempted. Hydropower averaged 36.7%, geothermal 20.7%, carbon capture and storage 14.9%, and bioenergy 10.7%; solar carried the least risk.

Then there is the mess the summaries make of it. Chinese-language write-ups of the same study report that the average project ran about 40% beyond plan with a delay of about two years — and they disagree on whether that 40% is construction cost or construction time. The substance barely moves; the presentation moves everything, because one result becomes two different numbers depending on which measure a summariser reaches for. That is the everyday condition of nuclear cost claims, and it is why a shared definition does more work than another study.

Other institutions land in the same place with less arithmetic. The IEA’s global review found high cost and long delays have to be addressed before nuclear can grow steadily. The Department of Energy’s advanced reactor liftoff report puts the ambition at roughly 550 to 770 GW of advanced nuclear for a net-zero United States in 2050, documents that overnight costs fall as designs move from first-of-a-kind to nth-of-a-kind, and — this is the line worth repeating in a boardroom — notes that perceived risk of uncontrolled overrun and project abandonment has limited committed orders for new reactors. An overrun is not only a cost. It is a demand suppressant.

Which is why loose numbers deserve suspicion. A widely shared Reddit post cites an analysis of 160,000 global megaprojects giving average cost overruns of 120% for nuclear and 238% for energy storage. Different sample, different definition, and the two datasets cannot both be describing the same quantity at the same scale. Until the underlying data and method are published, that 120% belongs in a footnote, not a slide.

What would a register have to record to be worth reading?

Start with the baseline: the budget and schedule fixed at final investment decision. Earlier figures are estimates, later ones are revisions, and only FID is a commitment. Each row needs capacity, reactor type, owner, host country and regulatory regime, a flag for first-of-a-kind status, and periodic deviation reports measured against that baseline. Cost and schedule belong in the same row, because a plant that finishes late and on budget fails differently from one that finishes on time and over budget, and only the pair tells you which one happened.

Coverage should run across generation technologies, with grid and storage reported alongside for context — a nuclear-only scoreboard would misdescribe a problem that shows up in hydro and geothermal too. And the register needs a written definition of overrun: nominal or real cost, which currency and exchange rate, and whether schedule is measured against a contractual date or a commercial operation target. Skip that and you have built a dispute generator rather than a database.

Here is the part that makes this practical rather than aspirational: some of the plumbing already exists. The IAEA’s Power Reactor Information System holds operating, under-construction and decommissioning status plus reactor specification data collected since 1969, and the agency rolled out a rebuilt version in 2026; its Advanced Reactors Information System covers designs that have no reference plant yet. What none of them publish is deviation against the budget and schedule fixed at FID — precisely the field that decides whether a pledge gets financed. The survey route is proven as well: the IEA and the OECD Nuclear Energy Agency’s Projected Costs of Generating Electricity has been assembled from government-submitted cost data across dozens of countries, most recently from 243 generating units in 24 countries, so the form-filling muscle already exists.

Two design choices carry most of the risk. Verification has to sit with a body that does not depend on the projects it audits, with audit rights and a published method — the OECD has already studied the governance frameworks that drive learning and continuous industrial performance in nuclear construction, which makes the IEA, the Nuclear Energy Agency or the OECD the natural host. And publication should be lagged for first-of-a-kind units and immediate for repeats. Tying the data to procurement and finance, so insurers, export credit agencies and utilities use it in their own decisions, gives owners a reason to report accurately instead of a reason to stall.

Small modular reactors need a category of their own rather than a footnote. Almost every SMR project is a first of its kind, the economics rest on factory production that has not yet happened at scale, and the public record is thin because so few units exist. Starting now, while the evidence is sparse, is the only way to find out whether the cost reductions in investor presentations survive construction. A register launched after the first fleet is ordered would only confirm what had already been paid for.

And a cost register is not the only ledger COP31 needs. Disclosing deviations says nothing about whether fuel supply and spent-fuel arrangements are in place, which is the readiness ledger for fuel and waste running in parallel to this one.

Wouldn’t publication raise the cost of capital for the first units?

Yes, at the margin — and that is the strongest objection, so it deserves a straight answer. Overnight costs fall as a design is repeated, so a first unit will always look worse than the fifth. Publish the first unit’s overrun and the next buyer’s lenders price it in; the cost of capital rises for units nobody has ordered yet, and the learning that would have brought costs down never happens. Transparency is not neutral.

The spread is already wide enough to absorb a lot of pricing. EY estimates the weighted average cost of capital for nuclear newbuilds at between 5% and 15%, against 5% to 8% for solar and wind — a range that reflects how much of the risk sits with the sponsor and the regime rather than the technology. Lenders and insurers already charge for undisclosed construction risk, and they charge it to every project in the queue, because they cannot separate a competent owner from a serial overrunner. A verified record moves that premium onto the projects that earn it and lowers borrowing costs for the builders who finish near schedule.

Campaigners have a stake too. The Cable reports that demonstrators at COP31 called nuclear “too risky, too slow, and too expensive to address the climate crisis”, and a permanent public ledger of delays is an efficient way to supply that argument with evidence. Comparability cuts the same way: reactors built in France, Turkey and the United States face different regulators, labour markets and supply chains, and a table ranking countries by average overrun would record context as competence.

So the objection is strong enough to change the design, not strong enough to abandon the instrument. Classification and a publication lag answer the learning-curve worry: a first-of-a-kind unit published with its status and a delay still tells the second buyer what to expect, without becoming the number that defines the whole programme.

Who should host it, and what should companies do before the next order?

The host is the whole ballgame. A body that depends on member governments for its budget will publish late and gently; a technical agency with an audit mandate will publish on time and embarrass someone, and that is what a delivery test looks like. A parallel from outside the power sector: the US Government Accountability Office reported that, as of June 2025, the National Nuclear Security Administration’s cumulative portfolio overrun had risen to $4.8 billion from $2.1 billion in 2023. Different business, same mechanic — the number exists, and is quotable, only because an outside auditor puts it in writing.

For readers who will be on the hook for the next order, the practical version looks like this:

  1. Utilities and developers: fix your FID baseline in a form that can survive external reading, and start producing deviation reports internally now, at the granularity you would want from a competitor — the first public disclosure should not be the first time your own board sees the number.
  2. Lenders, insurers and export credit agencies: ask for the deviation history on the sponsor’s previous units, not just this project’s feasibility study, and price the difference between a team that has delivered and one that has only modelled.
  3. Host-government policy teams: decide whether your country accepts third-party verification before you sign a reporting obligation, because a voluntary portal with self-reported numbers will not move the cost of capital.
  4. Procurement and legal: write the reporting duty into the EPC contract and the loan covenant — baseline, currency, schedule reference date, reporting cadence — so the data arrives as a contractual deliverable rather than as goodwill.

FAQ: What compliance and finance teams are asking

Does a register treat SMRs unfairly?

No — it treats them as first-of-a-kind by default, with a lag and a category of their own. The alternative, judging factory-built economics off a single site, is worse for everyone involved.

What actually counts as an overrun?

Only a deviation from the budget and schedule fixed at final investment decision, in a stated currency, nominal or real, with schedule measured against a named date. Everything else is a revision and should be labelled as one.

Who verifies the numbers if a government refuses to cooperate?

Publish what is verifiable, mark what is not, and let the gap show. A host with audit rights can treat “unverified” as a status rather than an omission, which is more informative than silence.

Is this a nuclear-only instrument?

No. Cross-technology coverage with grid and storage alongside is what makes the nuclear number interpretable at all.

Could it change anything before 2035?

Yes, if lenders start pricing off it. The 35x35 gap is decided by which units get financed in the next three or four ordering cycles, not by the units commissioned in 2034.

What to watch next

Three signals will tell you whether this becomes a working instrument or one more communiqué line. First, whether the 35x35 implementation text asks for delivery reporting at all, or stops at share targets. Second, who gets the secretariat — an IEA or NEA-style technical body with audit rights is a different animal from a voluntary industry portal. Third, whether insurers and export credit agencies pull the data into their own underwriting: that is the moment reporting stops being reputational and starts being priced.

Meanwhile the industry’s best defence is not an argument. It is a project that lands close to schedule, documented in enough detail that the next buyer can check the claim. If the first SMR fleet does that, a register becomes modest housekeeping. If it does not, the register becomes the thing everyone quotes at COP32. Either way the record is going to exist. The open question is who writes it — the builders, or somebody auditing them.

References

  • World Resources Institute: Countries Endorse 35x35 Electrification Pledge at COP31
  • UNFCCC: COP31 Presidency announces new targets on global electrification
  • Boston University Institute for Global Sustainability: Investment Risk for Energy Infrastructure Construction Is Highest for Nuclear Power Plants, Lowest for Solar
  • JD Supra: Department of Energy report on advanced reactors sets forth pathway to commercial liftoff
  • OECD: Unlocking Reductions in the Construction Costs of Nuclear
  • IAEA: Power Reactor Information System (PRIS)
  • EY: Capital costs challenge — how to overcome the issue in CESA nuclear power projects
  • RTO Insider: IEA Sees Momentum Toward New Nuclear Era, Obstacles
  • Tonghuashun Finance: IEA chief Birol says global nuclear capacity under construction hits 40-year high
  • SolarZoom: Boston University study on construction cost overruns by technology
  • The Cable: COP31 campaigners reject nuclear energy as climate solution
  • Reddit r/Futurology: A new analysis of 160,000 global megaprojects
Brand logo

Tech Daily

Your Daily Source for Consumer Tech, Policy & Communications

HardwarePolicy & RegulationSoftwareCommunicationsConsumer ElectronicsGeneralAPAC EdmGrowthAbout Us

© 2026 Tech Daily.

Cookie Notice

We use cookies to improve your experience and analyze website traffic. Read our Privacy Policy to learn more.