MyTechDailyNews PolicyAndRegulation: BAAJA Grid Gains May Be Undercounted as U.S. Review Slows

BAAJA's transmission provisions could increase U.S. new line capacity by 167% to 262% compared with the past decade, but Rhodium Group modeling may undercount that gain because it used energy-system estimates rather than a full network study. Today, MyTechDailyNews PolicyAndRegulation finds the deeper issue is grid review: interconnection studies and environmental review can be slower than Congress.

Public readers can trace the discussion to a Rhodium Group study analyzed in Heatmap Daily by Emily Pontecorvo and a colleague; the article was published by Heatmap. That framing matters for policy readers because BAAJA is not a single climate mandate. It is a permitting, planning, cost-allocation and interconnection package whose emissions effect depends on macroeconomic variables such as growth, fuel prices and load growth.

What does BAAJA change for U.S. transmission policy?

Transmission is the bottleneck through which most decarbonization scenarios must pass. Power lines move electricity from the sunniest and windiest regions to cities, towns and suburbs. Rhodium states that BAAJA could increase new transmission capacity added each year nationwide by 167% to 262% compared with the average rate over the past decade. That estimate reflects both affirmative grid expansion measures and changes to environmental review law.

Today, the practical regulatory signal is that transmission developers, grid operators and large-load customers should treat BAAJA as a planning instrument, not merely a political headline. The law's value is in what it asks federal agencies, FERC, state commissions and utilities to do differently: plan across regions, shorten federal review, reduce permit uncertainty and allocate more costs to beneficiaries.

IssueRhodium Group baselinePolicyAndRegulation reading
Transmission growthNew annual capacity could rise by 167% to 262% versus the past decade.A full network model could capture unlocks that energy-system modeling misses.
Review speedFederal environmental review for transmission takes twice as long as pipelines.Implementation may hinge on staffing, data quality and litigation exposure.
InterconnectionNot modeled at the line-and-substation level.BAAJA aims to let power plants join the grid in batches, compressing queues.
Data centersRatepayer protections appear in the broader model.Grid Strategies estimates $55 billion in data-center transmission charges over ten years.

Why might Rhodium be undercounting the benefits?

The Rhodium Group result is compelling but deliberately constrained. The authors did not build a full network model of the U.S. transmission grid. Such a study would account for physical footprint, power flows, congestion, substations and existing bottlenecks. Instead, they assessed power supply and demand within the broader energy system. This was reasonable. The bill was moving quickly, and weeks of deep modeling were not available without missing the legislative window.

That is also where the undercounting becomes possible. A transmission-specific network model could show that faster approvals do not simply add line miles; they unlock clusters of generation, storage and demand response that otherwise remain queued for interconnection. Foley Hoag, a law firm analyzing the Senate permitting bill, notes that BAAJA incentivizes utilities to apply grid-enhancing technologies to get more use out of the existing grid rather than unnecessarily building new corridors. If that incentive changes utility investment behavior, the modeled transmission gain may be too narrow because it does not fully represent avoided line buildouts and reactivated capacity.

How does grid review compare with Congressional speed?

The deeper irony is that clean energy projects are expected to perform studies that even a major policy shop cannot afford. When the National Renewable Energy Lab studied how quickly Los Angeles could switch to 100% renewable energy earlier this decade, it modeled every transmission line and substation in LA. Its supercomputer ran more than 100 million simulations, and the research effort took three years.

If Rhodium had tried to analyze BAAJA with that level of network detail, the result would have arrived after Congress had acted. The grid therefore creates a paradox: the sector that requires exhaustive studies to protect reliability also cannot supply equally exhaustive analysis to policymakers in time. The answer is not that the Rhodium Group estimate is wrong. The answer is that its method is conservative, transparent and bounded by time.

Interconnection studies amplify the problem. In many U.S. regions, a new solar farm or battery project must pass an interconnection study before joining the grid. The project must demonstrate how it affects congestion elsewhere. This process can slow the very resources that would otherwise benefit from expanded transmission. BAAJA aims to fix this by allowing power plants to join the grid in batches, a change that could shift the bottleneck from project review to queue management and regional planning.

Third Way summarizes modeling from C2ES suggesting that BAAJA's interconnection and transmission reforms could reduce emissions by 71 million metric tons, or 9%, by 2035. That number is not a substitute for a transmission network study, but it shows why the regulatory chain matters: faster review plus better planning plus cheaper power flows can reinforce each other.

What does data center cost allocation add?

Grid Strategies estimates that $55 billion in transmission costs could be collected from data centers over ten years under BAAJA's pricing reform, based on an assumption of roughly 40.3 GW of new data center demand outside Texas. This is important for policy readers because the Rhodium Group analysis mainly addresses system capacity and emissions; cost allocation changes who funds the expansion. For platforms, cloud providers and industrial buyers, the relevant risk is not whether the grid grows, but how transmission charges appear in power purchase agreements, colocation fees and sustainability reporting.

The Bipartisan Policy Center explains that BAAJA pushes FERC to revise pricing so customers pay in proportion to tangible benefits, while also giving FERC authority over imprudent utility transmission projects and fines of up to $5 million per imprudent project paid to states. That mechanism could reduce speculative cost passthroughs. It also means utilities will need stronger benefit documentation in filings.

What should companies do next?

  1. Build a transmission watchlist. Track FERC planning orders, state siting referrals, federal environmental review clocks and interconnection cluster rules, because BAAJA's effect will appear through procedures, not one headline.
  2. Model large-load exposure. Data-center, semiconductor and battery customers should price embedded and incremental transmission costs separately, using the Grid Strategies estimate as an upper-bound scenario rather than a fixed bill.
  3. Plan around batch interconnection. Developers should assume queues may be managed by zones and shared upgrade studies, which favors projects with complete engineering data, credible schedules and fewer localized objections.
  4. Document benefit allocation. Utilities and transmission owners should be ready to show how each project improves reliability, congestion or economic dispatch, especially when FERC can review imprudent cost recovery.
  5. Stress-test permitting risk. Even shorter review windows do not eliminate litigation, local opposition or land-use constraints; compliance teams should preserve administrative records and challenge standing early.

FAQ: What policy readers should remember

Is BAAJA a climate bill? It can affect emissions, but its design is a permitting and grid-planning reform. The Rhodium Group analysis treats the climate result as scenario-dependent, not guaranteed.

Why might the transmission upside be bigger? Because energy-system modeling can miss network effects such as unlocked projects, reactivated capacity, grid-enhancing technologies and cheaper regional power flows.

Why is grid review the slow part? Federal environmental studies, interconnection studies and reliability checks often require detailed modeling, and the National Renewable Energy Lab's Los Angeles work showed how costly that rigor can be when it is applied to an entire grid system.

Will data centers pay more? Grid Strategies says BAAJA could allow $55 billion in transmission costs to be collected from data centers over ten years. The practical effect depends on FERC rules, load forecasts and how contracts pass those charges through.

Reference sources

  • Rhodium Group, Estimating the US Energy System Impacts of BAAJA
  • Grid Strategies, Grid Funding from Data Centers in BAAJA
  • Bipartisan Policy Center, Explaining the Senate Permitting Bill
  • JD Supra, BAAJA Blast: What the Senate Permitting Bill Means for Transmission Developers
  • Third Way, On Permitting Reform: How To Talk About BAAJA
  • LADWP, LA100 Study
Brand logo

Tech Daily

Your Daily Source for Consumer Tech, Policy & Communications

HardwarePolicy & RegulationSoftwareCommunicationsConsumer ElectronicsGeneralAPAC EdmGrowthAbout Us

© 2026 Tech Daily.

Cookie Notice

We use cookies to improve your experience and analyze website traffic. Read our Privacy Policy to learn more.