By Sarah Chen · PolicyAndRegulation desk, MyTechDailyNews

The transmission title of the Bipartisan American Affordability and Jobs Act of 2026 regulates procedure, not power plants. It writes Federal Energy Regulatory Commission planning orders into statute, creates a federal siting backstop when states stall, and lets the regulator dock a utility’s return on equity for low-value local spending. Reliability, lower bills and fewer lawsuits are goods environmental groups, developers and ratepayer advocates all claim — which is why this title is the only part of the package without an organised opponent.
The rest of the bill is a different story. The intra-Democratic argument over permitting reform has grown sharper, with objections stacking up from tribes, elected officials and environmental organisations, yet the provisions covering lines, planning and cost allocation have quietly held their ground on both sides of the aisle.
Conclusion first: four linked obligations — plan regionally, permit with a federal backstop, allocate costs by benefit, and discipline utilities that do none of the above. That architecture is what draws support across the usual fault lines.
Christy Goldfuss, executive director of the Natural Resources Defense Council, wrote on X on Wednesday that her organisation “still sees great benefit in the transmission language that was negotiated,” hours after sounding alarms about other sections. John Podesta, the former Biden climate advisor, praised the bill’s “needed reforms on transmission” as “pretty good” and “pretty strong” before faulting other elements. Holly Bender of the Sierra Club listed the section as an example of “policies we’ve championed before.”
Industry is less equivocal. A coalition of five clean energy trade groups told congressional leaders in a letter: “The transmission provisions in BAAJA are essential to deploying more clean energy,” Climate philanthropist and investor Tom Steyer said the bill’s expanded transmission siting authority “means more power lines carrying more affordable energy to more people across America … which means lower bills for all of us.”
Because the cheapest new supply is stranded behind a permitting queue. About a month ago, New Mexico Senator Martin Heinrich, one of the two Democratic co-authors, introduced the bill publicly by turning first to the SunZia transmission project: a 550-mile line designed to carry 3.6 gigawatts of wind power — more electricity than the Hoover Dam generates and the largest renewable project in the country — from New Mexico to Arizona and California.
“That transmission line,” Heinrich said, “took 17 years to permit and build. That’s why I’m here today, because I was part of that process, which should have taken probably five years … We need to be able to build big things in this country again.” In an emailed statement he added: “Right now, clean, affordable energy is stuck waiting for transmission lines that take a decade or more to build, leaving Americans to pay sky-high utility bills,”
Geography does the rest. Clean generation sits where the rocks are hot (Utah), the sun shines (Nevada) or the wind blows (New Mexico), rather than where the electrons are consumed (California). David Pomerantz, executive director of the Energy and Policy Institute, put it plainly: “There’s effectively no way to have a high penetration renewable grid without a lot more regional and interregional transmission,” On this week’s episode of Shift Key he discussed the bill’s transmission section at length with Robinson Meyer.
Michael Skelly, co-founder and chief executive of transmission developer Grid United, argues the symbolism matters as much as the text: a bipartisan Congressional vote and presidential signature “would be an expression of the national sentiment that, for a whole variety of reasons, we need a better grid in the U.S.,”
Modelling from the energy research group RFF is what moved parts of the environmental coalition. The group released modelling showing BAAJA reducing emissions compared to the status quo through 2041. Aaron Bergman of RFF explained that transmission investment lets siting-sensitive wind power be “more competitive compared to some of the other technologies,” and added, “I confess before we did this, I actually did not expect to see the effect we saw,”
The same modelling sized the build-out: overall transmission capacity in the U.S. growing by over 30% by 2041, and “interregional capacity specifically is projected to grow by 10 to15 gigawatts per year between 2032 and 2041, leading to a rough doubling of capacity over the period modeled.” Delivering that would require the kind of planning overhaul that has been attempted for over 25 years with little success.
In short: agency policy becomes statute, and the statute gets teeth. BAAJA codifies — and therefore protects from legal challenge — existing orders by the Federal Energy Regulatory Commission around transmission planning, and requires regular transmission planning within and among regions. Skelly’s reading is blunt: “If you want a better grid in America, this is a hell of a bill to make that happen because it requires interregional planning,” He continued, pointing to mechanisms that let regions coordinate power-line development and establish a consistent way to allocate costs: “Those provisions are very, very helpful, and I think they’ll encourage a lot of activity in the transmission sector,”
The second lever is siting. FERC would be required to issue permits to interstate high-voltage lines, or lines using advanced conductoring, that meet certain public interest criteria after states get a year to act on a permit application. If BAAJA passed, FERC would also have to issue permits to lines that meet a national interest, reliability, and voltage criteria. For even higher voltage lines, transmission developers could apply for federal permits in parallel with the state permit, shortening the permitting timeline.
The third lever targets utilities. BAAJA gives force to the long-standing critique that utilities are overinvesting in transmission that is less useful to the whole system. States could refer utilities to FERC for investigation if they fail to pick cost-effective projects. If FERC determines that a utility’s planning is making it harder for regional transmission to get built, FERC could subsequently dock a utility’s return on equity, remove discretion from the utility for planning, or even issue fines.
The loophole those provisions chase is old. FERC had tried to coax utilities into building more transmission back in 2011. But when it issued an order to begin a competitive process for building new lines, it added exceptions for immediate reliability needs or building lines in your local territory. Daniel Palken, director of infrastructure at Arnold Ventures, has described how that exception “resulted in what was just mass gaming to the point where around 90% of the transmission built by utilities in the country over the last decade plus has fallen into those two categories,” His summary of the result: “So you’ve avoided building large-scale, efficient, economically driven transmission, and you’ve instead built incremental band-aids.”
Chirag Lala, vice president of research and chief economist at the Center for Public Enterprise, frames why statutory text is needed at all: “You’re talking about lines that can stretch across electricity markets, across utility jurisdictions. The sense among pretty much all electric system advocates is our current legal structure, for one reason or another, is totally insufficient to the task,”
The table below maps each lever against current practice and the party that would have to act.
| Regulatory lever | Practice today | Change under BAAJA | Who owns compliance |
|---|---|---|---|
| Planning duty | FERC planning orders rest on agency authority and can be revised or litigated away | Codified in statute; regular planning required inside and across regions | RTOs/ISOs, transmission developers |
| Siting authority | States hold line-siting power; FERC backstop is narrow and corridor-dependent | FERC must permit qualifying interstate or advanced-conductor lines after states get a year to act; national-interest criteria; parallel federal permits at higher voltage | Developers, state utility commissions |
| Cost allocation | Regional methods vary; local and reliability projects can be carved out | Consistent benefit-based allocation mechanisms backed by the regulator | Utilities, state legislatures |
| Investment discipline | State oversight of returns and project selection | FERC may dock return on equity, strip planning discretion, or fine a utility | Utility CFOs and rate-case teams |
| Litigation exposure | Long challenge windows; vacatur risk after a ruling | Law firms reading the bill describe a 150-day filing deadline and remand-without-vacatur as the default remedy | Project sponsors, environmental counsel |
| Large-load costs | Data-center-driven upgrades are often socialised across ratepayers | Pricing rules designed to keep the costs of big loads (generally 20 MW and up, per NRDC’s assessment) with the customers causing them | Hyperscalers, colocation operators, utilities |
The answer here is less obvious than it looks: the permitting title, not the transmission title, may do the most for lines. Transmission is notoriously hard to permit because it crosses many territories. In the West, where transmission is often most needed to connect far-flung wind, solar and geothermal resources to large urban areas, lines almost inevitably trip up the National Environmental Policy Act and the National Historic Preservation Act as they traverse public lands.
An analysis by Jack Andreasen Cavanaugh for Columbia University’s Center on Global Energy Policy found that transmission projects would see the largest time savings from the bill. Some of the biggest time savers come from FERC’s expanded ability to approve lines and from running National Historic Preservation Act reviews concurrently with the Environmental Impact Statement required by the National Environmental Policy Act. SunZia especially had an extremely drawn-out NHPA process that continued past the completion of construction of the line.
Candidates for the first build-out are already visible. Palken said, “Interregional planning has worked nowhere in the country in the last 15 years,” and while some regional planning has occurred, the Intermountain West could be a prime candidate going forward. Two of the bill’s authors, Republican Senator Mike Lee and Democratic Senator Martin Heinrich, represent the energy-rich adjacent states of Utah and New Mexico, respectively. The governors of Nevada and Utah, both Republicans, have endorsed the bill, while the governor of New Mexico, a Democrat, has not.
“The Intermountain West is both a growth region and a growth region that has seen virtually no transmission come out of FERC's existing processes,” Palken said.
Geothermal developers such as Fervo could benefit from western transmission investments. A recent short seller report identified transmission access as one reason to doubt the company’s prospects, because it will need to connect to customers in California. Jefferies analysts described transmission as an “execution item” for the company and noted that Fervo is “still working to secure roughly 100 MW” to serve Google as part of an offtake deal.
More broadly, if new load such as data centers is to be served by a clean grid, more transmission investment will be needed. Pomerantz said, “A lot of what we’re building now is wind and solar and, inherently, whatever you’re building more of needs the new transmission,”
Two things, not ideology: load growth and rising electricity rates. Experts have criticised the existing transmission planning system for as long as it has been cobbled together, but rising demand across the grid at least made bipartisan agreement on planning reform possible. Transmission has long been tagged in energy policy circles as a Democratic priority, because more long-range transmission could threaten utilities’ existing business models (and utilities were seen as quite influential among Republicans) and because transmission investments are needed to fully unlock wind and solar potential across the country, which Democrats tend to want to favour (and subsidise).
Travis Fisher, director of energy and environmental policy studies at the libertarian Cato Institute, said, “People are growing frustrated with utilities,” citing both rising costs and data-center-related investments leaking onto residential ratepayers’ bills.
Palken added the oversight angle: “There’s a lot of scrutiny on returns on investment. There’s this local transmission issue where there has really been a bipartisan sense among state and federal regulators that utilities have maybe gotten away with a lot of spending with almost no oversight from the state or federal government, and that, at a minimum, deserves looking into,”
Fisher told reporters the arithmetic changed for industry too: “It’s very clear that load growth is here to stay. So there’s a pro-industry argument for expanded transmission now that we didn't necessarily have before,” He also cited the sunsetting of Inflation Reduction Act subsidies for wind and solar as another reason Republicans could support the transmission title, because there was less fear that new transmission projects would supercharge the IRA’s subsidies.
“If you make it significantly easier to build long-range, high-voltage transmission lines, that is going to make it easier to put renewables on the grid,” Fisher said. “I don't think that's inherently bad, and you shouldn't oppose that if you’re a technology-neutral advocate like I am. But it does change the calculus when there’s significant subsidies on the table.”
Even if wind power is not receiving subsidies, new transmission investment can make it more economically viable. Bergman said, “Even absent further policies, transmission is very valuable for wind and it could lead to greater deployment and reductions in emissions,”
Directly: the bill is the first serious federal attempt to make new compute pay for the wires it needs — and that reshapes siting decisions for tech infrastructure. NRDC’s assessment of the package says it would direct FERC to develop pricing rules designed to prevent transmission costs created by data centers (generally 20 megawatts or more) from landing on other customers. Grid Strategies describes the mechanics: utilities charge data centers more for transmission service and use those additional revenues to reduce transmission charges for everyone else.
The economics that made this a live issue are documented. IEEFA found data centers were responsible for 63% of the increase in prices in the 2025/2026 PJM capacity auction, translating to roughly $9.3 billion in costs, and Utility Dive reported that data-center-driven capacity charges across the market’s last four base auctions totalled $29.4 billion — 46% of the $63.6 billion in total capacity cost. Regulators have been moving ahead of Congress: as White & Case noted, FERC issued show-cause orders in June 2026 requiring grid operators to revise or justify interconnection rules for data centers and other large loads.
For technology firms, that means transmission access, not just power purchase agreements, becomes a diligence item — the same constraint flagged around Fervo’s California connection. Public polling points the same way: Third Way reports that even after hearing arguments against it, 66% of voters support the permitting reform bill, a figure that helps explain why an idea widely called bureaucratic nonetheless has a politically defensible core.
No. It appropriates nothing for new lines and attaches no tax credit. It changes who must plan, who can issue a permit, who pays, and how long a project can be tied up in court. Bergman’s point is the practical consequence: subsidies are not required for transmission to shift the economics of wind.
It leaves states first but not final. States keep the opening move — FERC must act after states get a year to act on a permit application — while qualifying lines can also draw a federal permit on national-interest, reliability and voltage criteria. Analysts at the Bipartisan Policy Center note the sequencing constraint: the federal backstop process cannot begin until that period has run.
The trade-off is why environmental and tribal groups contest other titles of the bill even while accepting this one; historic-preservation and consultation reforms carry a very different risk profile for projects on public land.
Columbia’s analysis suggests transmission sees the largest time savings of any project class, mostly from concurrent National Historic Preservation Act review and expanded federal permitting rather than from any single deadline. SunZia’s NHPA process, which ran past the end of construction, is the reference case for how much slack the change removes.
The planning orders revert to contested agency policy rather than statute, and the siting backstop disappears with the session. Given the record — over 25 years of attempted overhaul — the realistic fallback is more incremental spending inside utility territories, which is precisely what Palken’s band-aid critique describes.
Set aside what the agreement proves. A bill that cannot satisfy its own party’s base on review and consultation can still pass on wires — so the transmission title is the durable artifact regardless of the final vote count, and it is the part of BAAJA worth reading as regulation rather than as politics.
Two signals point the same way for the next planning cycle. First, the modelling window runs through 2041, which means today’s load decisions are made against a decade-long build schedule, not a tariff quarter. Second, the enforcement tools — cost-allocation consistency, referrals, return-on-equity penalties — only matter if used, and the 2011 experience shows how quickly a procedural exception can hollow out a rule.
For technology companies, the takeaway is narrow and concrete: the binding constraint on new compute is moving from generation procurement to physical grid access, and the regulatory remedy now has a statutory path with a named deadline.
MyTechDailyNews’ PolicyAndRegulation desk maintains a running tracker of the bill’s floor movement and FERC follow-on rulemakings; readers who want the compliance brief can request it at hello@techdaily.com.